Exam4Training

Team members often do not work at the same time when completing their work on the tasks.You need to resolve the overallocations by using the Resource Leveling function.What should you do?

You are a project manager who uses Project Professional 2013.All resources in your project schedule have availability of 8 hours per day.You notice that several of the resources on the project are overallocated.You decide to level the project to help resolve the overallocations for the resources.

Team members often do not work at the same time when completing their work on the tasks.You need to resolve the overallocations by using the Resource Leveling function.What should you do?
A . Click the Level resources with a proposed booking type option.
B . Click the Level only within available slack option.
C . Click the Leveling can adjust individual assignments on a task option.
D . Click Clear Leveling.

Answer: C

Exit mobile version