How does technical debt impact product development?
How does technical debt impact product development?A . Without clearing technical debt, code complexity increases with time B. The code written becomes unusable when there is technical debt C. Product Owner may not be able to get additional funding if there is technical debt in the project D. It makes...
What is the time box for Nexus Sprint Planning?
What is the time box for Nexus Sprint Planning?A . 16 hours for one month Sprint B. 8 hours for one month Sprint C. 12 hours for one month Sprint D. It is up to the Nexus TeamView AnswerAnswer: D Explanation: It is not explicitly mentioned that Nexus Sprint planning...
What can be the result of this?
Teams want to integrate the code only before the Nexus Sprint Review. What can be the result of this? Select all that apply.A . There may be too many code conflicts while integration B. It will save Nexus members time C. There may be too little time to resolve integration...
Definition of Done is always same for Nexus and all individual Scrum Teams. True or False?
Definition of Done is always same for Nexus and all individual Scrum Teams. True or False?A . TRUE B. FALSEView AnswerAnswer: B Explanation: Individual Teams may choose more stringent Definition of Done.
Which are the three valid questions that can be discussed during Nexus Daily Scrum?
Which are the three valid questions that can be discussed during Nexus Daily Scrum?A . Was the previous day's work successfully integrated? B. What did I do yesterday towards Sprint Goal?View AnswerAnswer: A
What is the purpose of the Cross-Team Refinement event? Select two best answers.
What is the purpose of the Cross-Team Refinement event? Select two best answers.A . To select the Product Backlog items for the upcoming Sprint B. To refine the Product Backlog items granular enough for Scrum Teams to pull the work C. To determine a method to split the Product Backlog...
During Nexus Daily Scrum, a new issue has surfaced which can be resolved without outside help. Who should resolve the issue?
During Nexus Daily Scrum, a new issue has surfaced which can be resolved without outside help. Who should resolve the issue?A . Scrum Team members B. Nexus Integration Team members C. Scrum Master D. Nexus Daily Scrum MembersView AnswerAnswer: A Explanation: Since the issue has been discussed in the Nexus...
All the development team members need not attend Nexus Daily Scrum. True or False?
All the development team members need not attend Nexus Daily Scrum. True or False?A . FALSE B. TRUEView AnswerAnswer: B Explanation: Only selected representatives need to attend Nexus Daily Scrum.
Every team member of all the Scrum Teams must attend the Cross-Team Refinement event. True or False?
Every team member of all the Scrum Teams must attend the Cross-Team Refinement event. True or False?A . TRUE B. FALSEView AnswerAnswer: B Explanation: It is not mandatory for every member to attend the Cross-Team refinement event.
What is demonstrated during the Sprint Review in Nexus? Choose the BEST answer.
What is demonstrated during the Sprint Review in Nexus? Choose the BEST answer.A . There is no Sprint Review in Nexus B. Each team demonstrates the increment they built during the Sprint C. Only the key features of the integrated IncrementView AnswerAnswer: A Explanation: Nexus Sprint Review replaces the Sprint...