Which statement is true about batch size, lead time, and utilization?

Which statement is true about batch size, lead time, and utilization?A . Higher team member utilization leads to longer lead timesB . There is no direct relationship between lead time and utilizationC . As batch size increases, lead time decreasesD . There is no direct relationship between lead time and...

April 22, 2025 No Comments READ MORE +

If the distance between the arrival and departure curves on a team's cumulative flow diagram is growing apart, what is likely happening?

If the distance between the arrival and departure curves on a team's cumulative flow diagram is growing apart, what is likely happening?A . Lead time is increasingB . Unplanned work is pushed into the backlogC . WIP is decreasingD . The backlog is being reprioritizedView AnswerAnswer: A Explanation: Cumulative Flow...

April 9, 2025 No Comments READ MORE +

What goes into the Portfolio Backlog?

What goes into the Portfolio Backlog?A . Strategic ThemesB . ProjectsC . CapabilitiesD . EpicsView AnswerAnswer: D Explanation: The Portfolio Backlog in SAFe contains the larger initiatives, known as Epics. Epics are substantial pieces of work that require analysis, investment, and development effort over multiple Program Increments (PIs). They represent...

March 29, 2025 No Comments READ MORE +

Which two statements are true about a Feature? (Choose two.)

Which two statements are true about a Feature? (Choose two.)A . It is developed within a single Agile TeamB . It is fully completed by a single Agile Release Train within one PIC . It is prioritized using weighted shortest job firstD . It has one Capability as a parentView...

March 8, 2025 No Comments READ MORE +

What is a benefit of an Agile Release Train that has both cadence and synchronization?

What is a benefit of an Agile Release Train that has both cadence and synchronization?A . The Agile Release Train is able to control the injection on new workB . Dependencies are identified across the Agile Release TrainC . Teams participate in the portfolio backlog refinementD . The entire system...

March 2, 2025 No Comments READ MORE +

What is one output from the problem-solving workshop?

What is one output from the problem-solving workshop?A . ROAMed risksB . All the potential Solutions the team could identifyC . An assessment reportD . Top improvement items for the next PIView AnswerAnswer: D Explanation: One of the primary outputs from the problem-solving workshop in SAFe is identifying the top...

February 25, 2025 No Comments READ MORE +

How is average lead time measured in a Kanban system?

How is average lead time measured in a Kanban system?A . By taking the average velocity over the last three iterationsB . Measure the vertical distance between arrival and departure lines on a cumulative flow diagramC . Measure the horizontal distance between arrival and departure lines on a cumulative flow...

February 15, 2025 No Comments READ MORE +

Which of the SAFe Core Values enables trust across the ART?

Which of the SAFe Core Values enables trust across the ART?A . TransparencyB . AdaptationC . Built-in QualityD . Decentralized decision-makingView AnswerAnswer: A Explanation: SAFe Core Values are the fundamental beliefs that guide behaviors and decision-making in SAFe (Scaled Agile Framework). They are critical for fostering a culture that supports...

February 11, 2025 No Comments READ MORE +

What is one problem with phase-gate Milestones?

What is one problem with phase-gate Milestones?A . They assume a point Solution exists and can be built right the first timeB . They force design decisions too late in the processC . They account for variability inherent in the processD . They require the Product Owner to act as...

February 9, 2025 No Comments READ MORE +

What are two timestamps required to measure lead time when using a Team Kanban board? (Choose two.)

What are two timestamps required to measure lead time when using a Team Kanban board? (Choose two.)A . When the Story is released to users and validatedB . When the Story is deployedC . When the Agile Team pulls a Story onto the boardD . When the Story is accepted...

February 8, 2025 No Comments READ MORE +