Which of the following procedures should you removed?
XYZ Company hires you to make its transitioning procedure more effective in meeting close-out requirements. You review XYZ's transitioning procedures to eliminate any that do not belong in the close-out phase. Which of the following procedures should you removed?A . Managing the transition from the "As-ls" state to the "To-Be"...
What should the program manager do next?
The program manager has a global program with live component projects. The program sponsor wants the management plans, processes/procedures and technology to be uniform across the program. The requirements will create issues and result in increased costs. The program sponsor is new and has imposed these new requirements six months...
Which two of the following active equipment is included?
The type of apparatus housed in ERs vary greatly in size, purpose and function. Which two of the following active equipment is included? (Choose two.)A . Cross-connect facilities B. Telecommunications equipment C. Environmental controls D. Lighting controls E. Building system equipmentView AnswerAnswer: B,E
As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting?
A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting. As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)A . Project submittal approval process B. RFI process C. Payment procedures D. Punch List process...
What should the program manager do next?
The program sponsor returns from a board of directors meeting alter identifying a significant risk to the program schedule. This may Impact the program's benefits realization What should the program manager do next?A . Update the program benefits management plan and risk register B. Implement the mitigation plan for the...
Since the shutdown was not anticipated, what should the program manager do first?
A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of USS1 million. Since the shutdown was not anticipated, what should the program manager do first?A . Implement the appropriate risk response plan and inform the stakeholders of the planned...
What should the program manager do to address the risk?
A regional finance program is impacted by a new currency regulation issued by a country in the region. The new regulation requires changes to the financial statements of that country's branches by the end of the fiscal year Failing to comply with the regulation may result in fines and/or closure...
What should the program manager do next?
A municipal agency manages a city's water and wastewater infrastructure. A regulation requires the replacement of sewer lines throughout the city at a cost of US$2 billion over 30 years The city has been managing this program with various program teams, and has a project controls office In place to...
What should the program manager do next?
A program manager initiates a new global program to create a higher level of protection for a company's intellectual property. The company exhibits a relaxed culture and environment and is intolerant of processes to the point of being considered process-adverse However, the company's culture is tolerant of long-term program activities,...
What should the program manager do?
Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This...