Which metrics will help a Product Owner determine if a product is delivering value? (Choose the best two answers)

Which metrics will help a Product Owner determine if a product is delivering value? (Choose the best two answers)A . Productivity.B . Time to market.C . Velocity.D . Percentage of scope implemented.E . Customer satisfactionView AnswerAnswer: B, E

January 29, 2024 No Comments READ MORE +

When must the Product Owner participate in the Daily Scrum? (Choose the best answer)

When must the Product Owner participate in the Daily Scrum? (Choose the best answer)A . When there are impediments to discuss.B . When the Product Owner is actively working on items on the Sprint Backlog; however, they participate as a Developer.C . When the Scrum Master asks the Product Owner...

January 28, 2024 No Comments READ MORE +

True or False: Sprint Reviews are an opportunity to collect stakeholder feedback.

True or False: Sprint Reviews are an opportunity to collect stakeholder feedback.A . TRUEB . FALSEView AnswerAnswer: A

January 28, 2024 No Comments READ MORE +

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?A . The Sprint GoalB . Sprint Review minutes.C . The Sprint Backlog.D . The release plan.View AnswerAnswer: A

January 26, 2024 No Comments READ MORE +

What should the Scrum Master do?

Five new Scrum Teams have been created to build one product. A few of the Developers on One of the Scrum Teams ask the Scrum Master How to coordinate their work with the other teams. What should the Scrum Master do? (Choose the best answer)A . Teach the Product Owner...

January 26, 2024 No Comments READ MORE +

What enhances the transparency of an Increment? (choose the best answer)

What enhances the transparency of an Increment? (choose the best answer)A . Updating Sprint tasks properly in the electronic tracking tool.B . Keeping track of and estimating all undone work to be completed in a “hardening” Sprint.C . Reporting Sprint progress to the stakeholders daily.D . Doing all work needed...

January 26, 2024 No Comments READ MORE +

When should the Product Owner update the project plan? (Choose the best answer)

When should the Product Owner update the project plan? (Choose the best answer)A . The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.B . The project plan must be updated prior to the Sprint Retrospective.C . Before the Sprint Planning to know...

January 26, 2024 No Comments READ MORE +

How should a Development Team deal with non-functional requirements?

How should a Development Team deal with non-functional requirements?A . Make sure the release department understands these requirements, but it is not the Development Team's responsibility.B . Assign them to the lead developers on the team.C . Handle them during the Integration Sprint preceding the Release Sprint.D . Ensure every...

January 25, 2024 No Comments READ MORE +

True or False: Product Owners must create clear and unambiguous acceptance criteria for each Product Backlog item before it may be selected in Sprint Planning,

True or False: Product Owners must create clear and unambiguous acceptance criteria for each Product Backlog item before it may be selected in Sprint Planning,A . TRUEB . FALSEView AnswerAnswer: B

January 24, 2024 No Comments READ MORE +

What typically happens if the Product Backlog is not sufficiently clear at Sprint Planning? (Choose the best answer)

What typically happens if the Product Backlog is not sufficiently clear at Sprint Planning? (Choose the best answer)A . Sprint Planning is canceled so refinement can be done first.B . The Scrum Master should not allow this to happen. Look for a new Scrum Master and re-start the Sprint.C ....

January 24, 2024 No Comments READ MORE +