The "cone of uncertainty" can be used to do what? (Choose the best answer)

The "cone of uncertainty" can be used to do what? (Choose the best answer)A . Determine whether to cut quality, similar to the "Iron Triangle" of project management.B . Illustrate that as a project forecast lengthens, it is increasingly less certain.C . Determine the cost of a project before it...

September 13, 2024 No Comments READ MORE +

What should the Scrum Master do?

Fiv e new Scrum Teams have been created to build one p roduct. A few of the Developers on One of the Scrum Teams ask the Scrum Master How to coordinate their work with the other teams. What should the Scrum Master do? (Choose the best answer)A . Teach the...

September 12, 2024 No Comments READ MORE +

A Product Backlog is: (Choose the best three answers)

A Product Backlog is: (Choose the best three answers)A . Ordered based on priority, value, dependencies, and risk.B . Only visible to the Product Owner and stakeholders.C . An inventory of things to be done for the Product.D . An exaustive list of upfront approved requirements to be implemented.E ....

September 12, 2024 No Comments READ MORE +

Which metrics will help a Product Owner determine if a product is delivering value? (Choose the best two answers)

Which metrics will help a Product Owner determine if a product is delivering value? (Choose the best two answers)A . Productivity.B . Time to market.C . Velocity.D . Percentage of scope implemented.E . Customer satisfactionView AnswerAnswer: B, E

September 12, 2024 No Comments READ MORE +

True or False: Product Owners must specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.

True or False: Product Owners must specify complete acceptance criteria for a Product Backlog item before the Developers can select the item in Sprint Planning.A . TRUEB . FALSEView AnswerAnswer: B

September 11, 2024 No Comments READ MORE +

Scrum requires that the Product Owner must use which of the following items? (Choose all that apply)

Scrum requires that the Product Owner must use which of the following items? (Choose all that apply)A . Burndown chart.B . Feature bum-up.C . Critical Path Analysis.D . Project Gantt chart.E . None of the above.View AnswerAnswer: E

January 30, 2024 No Comments READ MORE +

Which of the following are the Developers accountable for? (Choose the best two answers)

Which of the following are the Developers accountable for? (Choose the best two answers)A . Selecting the Product Owner.B . Organizing the work required to meet the Sprint Goal.C . Creating a plan for the Sprint, the Sprint Backlog,D . Reporting productivity.View AnswerAnswer: B, C

January 29, 2024 No Comments READ MORE +

When can a Development Team cancel a Sprint?

When can a Development Team cancel a Sprint?A . When a technical dependency cannot be resolved.B . When the selected Product Backlog items for the Sprint become unachievable.C . When the Product Owner is absent too often.D . It cannot. Only Product Owners can cancel Sprints.E . When functional expectations...

January 29, 2024 No Comments READ MORE +

When many Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint?

When many Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint?A . No, each Scrum Team stands alone.B . Yes, but only for Scrum Teams whose work has dependencies.C . Yes, otherwise the Product Owners (and stakeholders) may not be able to...

January 29, 2024 No Comments READ MORE +

True or False: The value delivered by a product can only be determined by revenue.

True or False: The value delivered by a product can only be determined by revenue.A . TRUEB . FALSEView AnswerAnswer: B

January 29, 2024 No Comments READ MORE +