Which outcome is expected as a Scrum Team matures?

Which outcome is expected as a Scrum Team matures? (choose the best answer)A . There will be no need for a time boxed Sprint.B . They will improve their Definition of Done to include more stringent criteria.C . The Sprint Retrospectives will grow to be longer than 4 hours.D ....

January 20, 2024 No Comments READ MORE +

Who is accountable for managing the progress of work during a Sprint? (Choose the best answer)

Who is accountable for managing the progress of work during a Sprint? (Choose the best answer)A . The Product Owner.B . The Developers.C . The Scrum Master.D . The most junior member of the team.View AnswerAnswer: B

January 18, 2024 No Comments READ MORE +

How much time must a Product Owner spend with the Developers? (Choose the best answer)

How much time must a Product Owner spend with the Developers? (Choose the best answer)A . 40%, or more if the stakeholders agree.B . Enough so that the Product Owner is confident the Increment will meet the intended value.C . As much time as the Developers tell the Product Owner...

January 18, 2024 No Comments READ MORE +

Every Scrum Team should have: (Choose the best answer)

Every Scrum Team should have: (Choose the best answer)A . One Lead Developer and no more than 8 other members.B . The competencies and skills needed to deliver an Increment in a Sprint.C . At least one representative from each major department, such as, Quality Assurance, Development, and Marketing.View AnswerAnswer:...

January 17, 2024 No Comments READ MORE +

Does this mean that the Product Owner has final say over the Definition of Done?

The Product Owner is the person who will be held accountable if a product does not achieve its goals or deliver value. Does this mean that the Product Owner has final say over the Definition of Done? (Choose the best answer)A . Yes, the Product Owner decides the Definition of...

January 17, 2024 No Comments READ MORE +

How much of the Sprint Backlog must be defined during the Sprint Planning event? (Choose the best answer)

How much of the Sprint Backlog must be defined during the Sprint Planning event? (Choose the best answer)A . Enough so the Developers can create their forecast of what work they can do.B . Just enough tasks for the Scrum Master to be confident in the Developers' understanding of the...

December 26, 2023 No Comments READ MORE +

Every Scrum Team should have: (Choose the best answer)

Every Scrum Team should have: (Choose the best answer)A . One Lead Developer and no more than 8 other members.B . The competencies and skills needed to deliver an Increment in a Sprint.C . At least one representative from each major department, such as, Quality Assurance, Development, and Marketing.View AnswerAnswer:...

December 25, 2023 No Comments READ MORE +

Which outcome is expected as a Scrum Team matures?

Which outcome is expected as a Scrum Team matures? (choose the best answer)A . There will be no need for a time boxed Sprint.B . They will improve their Definition of Done to include more stringent criteria.C . The Sprint Retrospectives will grow to be longer than 4 hours.D ....

December 25, 2023 No Comments READ MORE +

True or False: Sprint Reviews are an opportunity to collect stakeholder feedback.

True or False: Sprint Reviews are an opportunity to collect stakeholder feedback.A . TRUEB . FALSEView AnswerAnswer: A

December 24, 2023 No Comments READ MORE +

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?A . The Sprint GoalB . Sprint Review minutes.C . The Sprint Backlog.D . The release plan.View AnswerAnswer: A

December 24, 2023 No Comments READ MORE +