How is management external to the Scrum Team involved in the Daily Scrum?
How is management external to the Scrum Team involved in the Daily Scrum?A . The Scrum Master speaks on their behalf.B . The Development Team self-manages and is the only management required at the Daily Scrum.C . Management gives an update at the start of each Daily Scrum.D . The...
Which of the following are true about the length of the Sprint? (Choose two.)
Which of the following are true about the length of the Sprint? (Choose two.)A . The length of the Sprint should be proportional to the work that is done in between Sprints.B . It is best to have Sprints of consistent length throughout a development effort.C . Sprint length is...
Which of the following two actions should the Scrum Master support?
In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn’t figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able...
What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose two.)
What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose two.)A . Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.B . Add security concerns to the definition of “Done”.C . Add a...
Which two activities will a Product Owner engage in during a Sprint? (Choose two.)
Which two activities will a Product Owner engage in during a Sprint? (Choose two.)A . Run the Daily Scrum.B . Prioritize the Development Team’s work on the Sprint Backlog.C . Update the Sprint burndown chart.D . Answer questions from the Development Team about items in the current Sprint.E . Work...
Who creates a Product Backlog Item’s estimate?
Who creates a Product Backlog Item’s estimate?A . The Development Team after clarifying requirements with the Product Owner.B . The Product Owner with input from the Development Team.C . The most senior people in the organization, including architects and subject matter experts.D . The Scrum Master.E . The Development Team,...
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the...
Scrum has a role called “Project Manager”.
Scrum has a role called “Project Manager”.A . TrueB . FalseView AnswerAnswer: B Explanation: The correct answer is B, because there is no role called “Project Manager” in Scrum. The Scrum Guide states that “Scrum recognizes no titles for Development Team members other than Developer, regardless of the work being...
Which of the following is required by Scrum? (Choose all that apply.)
Which of the following is required by Scrum? (Choose all that apply.)A . Sprint Retrospective.B . Members must be stand up at the Daily Scrum.C . Sprint Burndown Chart.D . Release planning.E . All of the above.View AnswerAnswer: AD Explanation: According to the Scrum Guide1, the only required events in...
Who must attend the Daily Scrum?
Who must attend the Daily Scrum?A . The Scrum Master and Product Owner.B . The Development Team.C . The Development Team and Product Owner.D . The Scrum Team.E . The Development Team and Scrum Master.View AnswerAnswer: D Explanation: According to the Scrum Guide1, the Daily Scrum is an event for...