Which 2 statements should be recorded under the Expected dis-benefits heading?
Which 2 statements should be recorded under the Expected dis-benefits heading?A . An investment of £2.5m is required.B . Staff morale will be negatively affected.C . The project will take two years to deliver.D . Staff may lose the opportunity to work in Information Technology.E . MFH will lose direct...
Which of the following activities is the Executive responsible for?
Which of the following activities is the Executive responsible for?A . Ensure the desired outcome of the project is specifiedB . Responsible for the benefits review planC . Assess and update the Business Case at the end of each stageD . Responsible for the Benefits Review Plan post projectView AnswerAnswer:...
Who should approve this update?
The project is at the end of stage 4. The project manager has changed the benefits management approach. It now includes all the activities necessary to measure the increased revenue. Who should approve this update?A . Corporate managementB . Project boardC . Project assuranceD . Project managerView AnswerAnswer: B
Who should approve the external supplier’s team plan?
The development of the ‘e-learning course’ will be outsourced to an external supplier and their key members will join the project management team. The supplier wants to keep their work processes confidential and not share these with ABC Company. ABC Company has agreed. Who should approve the external supplier’s team...
Is this appropriate, and why?
ABC Company carried out a similar project two years ago, in response to changes in health and safety legislation for the health service. The experiences from that project were used to refine the corporate risk management policy. For that reason, the project board decided to use the corporate risk management...
Is this an appropriate application of the ‘continued business justification’ principle?
During stage 3, project costs are increasing but there will still be a positive return on investment, as documented in the business case. However, corporate management has recently revised its targets for return on investment and has decided to stop the project as it will not meet the new targets....
Which principle is being applied, and why?
During stage 3, a work package was assigned to produce the 'planned pilot courses'. The product's quality criteria were defined and baselined before the work package was agreed. Which principle is being applied, and why?A . 'Focus on products', because delivering a product's complete set of features is more important...
Is this an appropriate application of the ‘learn from experience’ principle, and why?
One of the senior managers of the company that is developing the ‘e-learning course’ has worked with ABC Company before. The team manager for the delivery of the ‘e-learning course’ has looked on ABC Company’s intranet, but cannot find any reference to this work. The team manager has contacted the...
Is this an appropriate action for the project board, and why?
ABC Company has decided to include the Health and Safety Training Project in a programme to support their strategy to deliver globally. The programme team has provided the detailed business justification and, as a result, the project board has decided that the business case will not need refining further during...
Which 2 statements explain why the Purchasing Manager should be appointed as a Senior Supplier for this project?
Which 2 statements explain why the Purchasing Manager should be appointed as a Senior Supplier for this project?A . He is responsible for the organization's procurement activates.B . He is responsible for the performance of supplier contracts.C . He was an engineer and worked in that area before taking up...