Which is a purpose of the quality theme?
Which is a purpose of the quality theme?A . To define the specific conditions that enable a product to be usableB . To determine how the means of delivering products is communicatedC . To evaluate whether the project continues to be achievableD . To assess any potential improvements to a...
Which is often used during a retrospective to capture lessons?
Which is often used during a retrospective to capture lessons?A . A Glad! Sad! Mad! boardB . A Kanban boardC . A burn chartD . A Gantt chartView AnswerAnswer: A Explanation: Reference: https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_120&showNav=true&expandNav=true
Which process can take place during a release review workshop?
Which process can take place during a release review workshop?A . Controlling a stageB . Managing product deliveryC . Managing a stage boundaryD . Directing a projectView AnswerAnswer: B
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?A . Using visualization to display informationB . Using meeting minutes to share decisionsC . Using social media to reach more peopleD . Using email to document discussionsView AnswerAnswer: A Explanation: Reference: https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_165&showNav=true&expandNav=true
Which statement about the ‘embrace change’ target is CORRECT?
Which statement about the ‘embrace change’ target is CORRECT?A . It minimizes the time needed to train a new team memberB . It reduces the planning of dependencies between projectsC . It reduces testing in order to meet deadlinesD . It encourages the customer to raise new ideasView AnswerAnswer: D...