Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?A . Those with a financial interest in the projectB . Those who will manage the project on a day-to-day basisC . Those who will specify the desired outputs of the projectD . Those who...
Whose approval is needed to replace a Stage Plan with an Exception Plan?
Whose approval is needed to replace a Stage Plan with an Exception Plan?A . Corporate or programme managementB . Project BoardC . Project ManagerD . Team ManagerView AnswerAnswer: B Explanation: The approval needed to replace a Stage Plan with an Exception Plan must come from the Project Board. This is...
Which should be funded from a change budget?
Which should be funded from a change budget?A . The Starting up a Project processB . A fallback planC . An agreed change to the scope of a projectD . A change to a plan, within allocated tolerances, due to poor estimatingView AnswerAnswer: C Explanation: Similar to the answer to...
Which is a type of issue?
Which is a type of issue?A . A lessonB . A request for changeC . An Exception ReportD . A risk with an estimated high impactView AnswerAnswer: B Explanation: In the PRINCE2 framework, a type of issue that can commonly occur is a request for change. This refers to a...
Which characteristic distinguishes a project from regular business operations?
Which characteristic distinguishes a project from regular business operations?A . Produces benefitsB . Introduces business changeC . Manages stakeholdersD . Incurs costView AnswerAnswer: B Explanation: A characteristic that distinguishes a project from regular business operations is that it introduces business change. Projects are temporary endeavors undertaken to create a unique...
Which is a true statement about time-driven controls?
Which is a true statement about time-driven controls?A . Time-driven controls are used for monitoring the progress of Work Packages and management stagesB . Time-driven controls take place when specific events happenC . Time-driven controls are produced at the end of a stageD . An Exception Report is a time-driven...
Which is a purpose of the Initiating a Project process?
Which is a purpose of the Initiating a Project process?A . Decide if it is worthwhile to initiate a projectB . Decide on the project approachC . Establish solid foundations for a projectD . Identify the number of Work Packages requiredView AnswerAnswer: C Explanation: The purpose of the Initiating a...
Which is a benefit of using PRINCE2?
Which is a benefit of using PRINCE2?A . Enables the management of projects as well as of 'business as usual' activitiesB . Can be tailored by leaving out elements of the method for some projectsC . Can be applied to any type of projectD . Avoids the need to involve...
What theme estimates the cost of delivering the project?
What theme estimates the cost of delivering the project?A . Business CaseB . ChangeC . PlansD . ProgressView AnswerAnswer: C Explanation: The Plans theme in PRINCE2® is responsible for estimating the cost of delivering the project. This theme involves the development of plans that outline how, when, and by whom...
What product defines the reporting requirements between the Project Manager and Team Manager?
What product defines the reporting requirements between the Project Manager and Team Manager?A . Project BriefB . Product DescriptionC . Team PlanD . Work PackageView AnswerAnswer: D Explanation: The Work Package is the product that defines the reporting requirements between the Project Manager and the Team Manager. It describes the...