Which process covers the work done by external suppliers who may NOT be using PRINCE2?
Which process covers the work done by external suppliers who may NOT be using PRINCE2?A . Closing a ProjectB . Managing a Stage BoundaryC . Managing Product DeliveryD . Directing a ProjectView AnswerAnswer: C Explanation: The Managing Product Delivery process in PRINCE2 covers the work done by external suppliers, even...
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?A . Corporate groupB . Project BoardC . Project AssuranceD . ExecutiveView AnswerAnswer: A Explanation: The information in a Lessons Report should be used by the corporate group to refine,...
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?A . Directing a ProjectB . Managing a Stage BoundaryC . Controlling a StageD . Starting up a ProjectView AnswerAnswer: C Explanation: The Controlling a Stage process in PRINCE2 ensures focus on the delivery of a...
Which is a typical core activity within configuration management?
Which is a typical core activity within configuration management?A . Quality assuranceB . Risk managementC . Verification and auditD . Progress reportingView AnswerAnswer: C Explanation: Verification and audit is a typical core activity within configuration management according to PRINCE2. This activity involves checking that products meet their requirements and are...
Which is NOT one of the PRINCE2 integrated elements?
Which is NOT one of the PRINCE2 integrated elements?A . Tailoring PRINCE2 to the project environmentB . The processesC . The productsD . The themesView AnswerAnswer: C Explanation: In the context of PRINCE2, the integrated elements include the principles, themes, processes, and tailoring PRINCE2 to the project environment. 'The products'...
If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.A . Only 1 is trueB . Only 2 is trueC . Both 1 and 2 are trueD . Neither 1 or 2 are trueView AnswerAnswer: C Explanation: Both statements are true...
How many roles make up the Project Board?
How many roles make up the Project Board?A . OneB . TwoC . ThreeD . FourView AnswerAnswer: C Explanation: The Project Board within the PRINCE2® framework is made up of three key roles: the Executive, the Senior User, and the Senior Supplier. These roles represent the business, user, and supplier...
From whom does a Team Manager obtain approval for a completed product?
From whom does a Team Manager obtain approval for a completed product?A . Project ManagerB . Project SupportC . The authority defined in the Product DescriptionD . Senior SupplierView AnswerAnswer: A Explanation: In the PRINCE2® methodology, the Team Manager obtains approval for a completed product from the Project Manager. The...
Which is a purpose of the Controlling a Stage process?
Which is a purpose of the Controlling a Stage process?A . Assign work to be done and take corrective action to ensure that the stage remains within toleranceB . Provide a fixed reference point at which acceptance for the project product is confirmedC . Enable the Project Board to be...
Which does the Executive need to ensure is in place before the project is initiated?
Which does the Executive need to ensure is in place before the project is initiated?A . All Work Packages are authorizedB . An understanding of how the project will contribute to corporate objectivesC . The Project Plan has been approvedD . The Project Initiation Documentation is completeView AnswerAnswer: B Explanation:...