Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.

Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.A . define a coding system to provide a unique identifier for the products withinB . summarize the results of the quality activities performed onC . provide a framework...

September 30, 2024 No Comments READ MORE +

Which is a purpose of the Directing a Project process?

Which is a purpose of the Directing a Project process?A . Create and authorize the project mandateB . Ensure that work on products allocated to the team is authorized and agreedC . Control the day-to-day running of the projectD . Delegate day-to-day management of the project to the Project ManagerView...

September 30, 2024 No Comments READ MORE +

What first action should be taken?

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?A . Raise a request for changeB . Raise an off-specificationC . Write an Exception ReportD . Amend the Work PackageView AnswerAnswer: B Explanation: When a product cannot...

September 30, 2024 No Comments READ MORE +

Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?A . Off-specificationsB . Follow-on action recommendationsC . Issue RegisterD . Risk RegisterView AnswerAnswer: B Explanation: Follow-on action recommendations are used to document any uncompleted work or additional...

September 30, 2024 No Comments READ MORE +

Which is a purpose of the Closing a Project process?

Which is a purpose of the Closing a Project process?A . Authorize the final stage of the projectB . Confirm that all benefits defined in the Business Case have been achievedC . Recognize whether objectives set out in the original Project Initiation Documentation have been achievedD . Delegate day-to-day management...

September 30, 2024 No Comments READ MORE +

How many management stages should a PRINCE2 project consist of?

How many management stages should a PRINCE2 project consist of?A . Start up stage, initiation stage and at least one other management stage to cover the remainder of the projectB . Start up stage, at least one other management stage to cover the remainder of the project and a closing...

September 29, 2024 No Comments READ MORE +

Which is a typical core activity within configuration management?

Which is a typical core activity within configuration management?A . Issue managementB . Quality inspectionC . IdentificationD . PreparationView AnswerAnswer: C Explanation: Identification is one of the core activities within configuration management in the PRINCE2 methodology. This activity entails defining and identifying the configuration items within a project, documenting their...

September 29, 2024 No Comments READ MORE +

Which statement about the Directing a Project process is true?

Which statement about the Directing a Project process is true?A . Provides a mechanism for the Project Board to assure that there is continued business justificationB . Covers the day-to-day activities of the Project ManagerC . Ensures there are regular progress meetingsD . Begins on completion of the Initiating a...

September 29, 2024 No Comments READ MORE +

Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?

Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?A . Specify the desired resultB . Provide the resources and skills to deliver the desired resultC . Ensure the technical integrity of a projectD . Develop a project's productsView AnswerAnswer: A Explanation: In the PRINCE2 customer/supplier environment,...

September 28, 2024 No Comments READ MORE +

How many roles make up the Project Board?

How many roles make up the Project Board?A . OneB . TwoC . ThreeD . FourView AnswerAnswer: C Explanation: The Project Board within the PRINCE2® framework is made up of three key roles: the Executive, the Senior User, and the Senior Supplier. These roles represent the business, user, and supplier...

September 28, 2024 No Comments READ MORE +