Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.
Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.A . Management strategiesB . PlanC . Stakeholder interestsD . Time-driven controlsView AnswerAnswer: B Explanation: PRINCE2® recommends three levels of planning...
The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.A . Only 1 is trueB . Only 2 is trueC . Both 1 and 2 are trueD . Neither 1 or 2 are trueView AnswerAnswer:...
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?A . BenefitsB . QualityC . RiskD . ScopeView AnswerAnswer: B Explanation: Quality is the aspect of project performance that must be managed to ensure the project's products are fit for purpose. PRINCE2® emphasizes...
Which product identifies the management stages and timescales of a project?
Which product identifies the management stages and timescales of a project?A . Project BriefB . Project Product DescriptionC . Project PlanD . Initiation Stage PlanView AnswerAnswer: C Explanation: The Project Plan in PRINCE2 identifies the management stages and timescales of a project. This plan provides an overview of how and...
Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?A . ExecutiveB . Senior UserC . Senior SupplierD . Project ManagerView AnswerAnswer: B Explanation: The Senior User within the PRINCE2 project management team represents the...
Which is the purpose of the Change theme?
Which is the purpose of the Change theme?A . Prevent change to baselined productsB . Identify, assess and control any potential and approved changes to baselined productsC . Establish mechanisms to monitor and compare actual achievements against those plannedD . Assess and control uncertaintyView AnswerAnswer: B Explanation: The purpose of...
Which is a purpose of the Directing a Project process?
Which is a purpose of the Directing a Project process?A . Provide the information required to confirm if it is worthwhile to initiate a projectB . Enable overall control of a project to be exercised by the Project BoardC . Establish the level of control required by the Project Board...
Which is a benefit of using PRINCE2?
Which is a benefit of using PRINCE2?A . Is a method specifically designed for technical projectsB . Provides for the efficient and economic use of management timeC . Includes many of the proven planning techniques, such as critical path analysisD . Can be used to manage both projects and programmesView...
Which is a purpose of the Managing Product Delivery process?
Which is a purpose of the Managing Product Delivery process?A . Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work PackageB . Provide a controlled link between the Project Manager and the Team Manager(s)C...
Which is NOT a purpose of a Benefits Review Plan?
Which is NOT a purpose of a Benefits Review Plan?A . Define the period over which the cost-benefit analysis will be basedB . Describe how to measure the performance of the project's products in operational useC . Define the scope, timing and ownership of the benefit reviews requiredD . Describe...