What is an off-specification?

What is an off-specification?A . A new requirementB . A quality toleranceC . A type of issueD . A major riskView AnswerAnswer: C Explanation: An off-specification in PRINCE2 is considered a type of issue that arises when a project deliverable is forecasted to deviate from its agreed-upon specifications or requirements....

October 5, 2024 No Comments READ MORE +

How should the Team Manager report that tolerances are forecast to be exceeded?

How should the Team Manager report that tolerances are forecast to be exceeded?A . Create an Exception ReportB . Create a Highlight ReportC . Raise an issueD . Grant a concessionView AnswerAnswer: A Explanation: The correct procedure for a Team Manager to report that tolerances are forecast to be exceeded...

October 5, 2024 No Comments READ MORE +

Which is a purpose of a Lessons Log?

Which is a purpose of a Lessons Log?A . Note any lessons that are raised in Checkpoint ReportsB . Record that corrective action is being takenC . Escalate lessons to the Project BoardD . Raise improvements with Project AssuranceView AnswerAnswer: A Explanation: The purpose of a Lessons Log in PRINCE2®...

October 5, 2024 No Comments READ MORE +

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

Which process is triggered towards the end of the final stage when all the assigned work has been completed?A . Managing a Stage BoundaryB . Managing Product DeliveryC . Closing a ProjectD . Controlling a StageView AnswerAnswer: C Explanation: The Closing a Project process in PRINCE2 is triggered towards the...

October 4, 2024 No Comments READ MORE +

Which should be funded by a change budget?

Which should be funded by a change budget?A . Increase in agreed scopeB . Initiation stageC . Change AuthorityD . Handover activitiesView AnswerAnswer: A Explanation: The change budget in a PRINCE2® project is designed to fund changes that involve an increase in the agreed scope of the project. Such changes...

October 4, 2024 No Comments READ MORE +

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.A . project cost toleranceB . stage cost toleranceC . Work Package cost toleranceD . product cost toleranceView AnswerAnswer: C Explanation: A Project Manager agrees on the Work Package cost tolerances...

October 4, 2024 No Comments READ MORE +

What is the collective name for individuals or groups who may be affected by a project?

What is the collective name for individuals or groups who may be affected by a project?A . CustomersB . Project SupportC . StakeholdersD . Team membersView AnswerAnswer: C Explanation: In PRINCE2, the collective name for individuals or groups who may be affected by or can influence a project is "Stakeholders."...

October 4, 2024 No Comments READ MORE +

Which plan provides the Business Case with costs during the Initiating a Project process?

Which plan provides the Business Case with costs during the Initiating a Project process?A . Initiation Stage PlanB . Project PlanC . Stage PlanD . Team PlanView AnswerAnswer: B Explanation: During the Initiating a Project process in PRINCE2, the Project Plan provides the Business Case with necessary details, including cost...

October 4, 2024 No Comments READ MORE +

Which is NOT a purpose of a Benefits Review Plan?

Which is NOT a purpose of a Benefits Review Plan?A . Define the period over which the cost-benefit analysis will be basedB . Describe how to measure the performance of the project's products in operational useC . Define the scope, timing and ownership of the benefit reviews requiredD . Describe...

October 4, 2024 No Comments READ MORE +

The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.A . Only 1 is trueB . Only 2 is trueC . Both 1 and 2 are trueD . Neither 1 or 2 are trueView AnswerAnswer: C Explanation: Both statements...

October 4, 2024 No Comments READ MORE +