How many tasks does the product-based planning technique describe?

How many tasks does the product-based planning technique describe?A . OneB . TwoC . ThreeD . FourView AnswerAnswer: D Explanation: The product-based planning technique described in PRINCE2 involves four tasks: writing the Project Product Description, creating the product breakdown structure, writing product descriptions, and creating the product flow diagram. These...

September 13, 2024 No Comments READ MORE +

Which statement about stages is true?

Which statement about stages is true?A . Management stages should be of the same durationB . The use of technical stages is mandatoryC . The use of management stages is mandatoryD . Management stages are driven by specialist teamsView AnswerAnswer: C Explanation: PRINCE2® mandates the use of management stages in...

September 12, 2024 No Comments READ MORE +

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?A . Only corporate or programme managementB . Only the Project BoardC . Only the Project ManagerD . All levels of managementView AnswerAnswer: D Explanation: The mechanisms established by the Progress theme in PRINCE2...

September 12, 2024 No Comments READ MORE +

Which is a FALSE statement about technical stages?

Which is a FALSE statement about technical stages?A . Can overlap with other technical stagesB . Typified by the use a particular set of specialist skillsC . Include the Managing a Stage Boundary process activitiesD . Can span more than one management stageView AnswerAnswer: C Explanation: The statement that technical...

September 12, 2024 No Comments READ MORE +

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?A . Create a separate Project Board to manage the supplier elements of the projectB . Create multiple smaller Project Boards during the process of Starting up...

September 12, 2024 No Comments READ MORE +

Which product documents the information needed to demonstrate continued business justification?

Which product documents the information needed to demonstrate continued business justification?A . Business CaseB . Communication Management StrategyC . Project Product DescriptionD . Quality Management StrategyView AnswerAnswer: A Explanation: The Business Case in PRINCE2® documents the information needed to establish and maintain a project's continued business justification. It includes details...

September 12, 2024 No Comments READ MORE +

In what process is the authorization to deliver the project's products given?

In what process is the authorization to deliver the project's products given?A . Starting up a ProjectB . Initiating a ProjectC . Managing a Stage BoundaryD . Directing a ProjectView AnswerAnswer: D Explanation: The authorization to deliver the project's products is given during the Directing a Project process. This process...

September 11, 2024 No Comments READ MORE +

Which two roles are linked by the Managing Product Delivery process?

Which two roles are linked by the Managing Product Delivery process?A . Corporate or programme management and Project BoardB . Project Board and Project ManagerC . Project Manager and Team ManagerD . Team Manager and external supplierView AnswerAnswer: C Explanation: The Managing Product Delivery process in PRINCE2 links the Project...

September 11, 2024 No Comments READ MORE +