Which is a true statement about time-driven controls?

Which is a true statement about time-driven controls?A . Time-driven controls are used for monitoring the progress of Work Packages and management stagesB . Time-driven controls take place when specific events happenC . Time-driven controls are produced at the end of a stageD . An Exception Report is a time-driven...

September 19, 2024No CommentsREAD MORE +

Which is one of the six aspects of project performance that needs to be managed?

Which is one of the six aspects of project performance that needs to be managed?A . ProgressB . ChangeC . RiskD . SecurityView AnswerAnswer: A Explanation: Among the six aspects of project performance that need to be managed according to PRINCE2®, 'Progress' is a key component. The other aspects include...

September 19, 2024No CommentsREAD MORE +

Which statement about the Directing a Project process is true?

Which statement about the Directing a Project process is true?A . Provides a mechanism for the Project Board to assure that there is continued business justificationB . Covers the day-to-day activities of the Project ManagerC . Ensures there are regular progress meetingsD . Begins on completion of the Initiating a...

September 19, 2024No CommentsREAD MORE +

Which is one of the three levels of plan in PRINCE2?

Which is one of the three levels of plan in PRINCE2?A . Benefits Review PlanB . Programme PlanC . Team PlanD . Project BriefView AnswerAnswer: C Explanation: PRINCE2® defines three levels of planning: Project Plan, Stage Plan, and Team Plan. The Team Plan is one of these three levels, specifically...

September 19, 2024No CommentsREAD MORE +

Which is the Issue Register NOT used for?

Which is the Issue Register NOT used for?A . Capture external events that are impacting a stageB . Record information about a deviation in stage toleranceC . Capture any threats or opportunities that might have an impact on a stageD . Record any problems identified when authorizing a Work PackageView...

September 18, 2024No CommentsREAD MORE +

What process aims to ensure accurate progress information is provided to the Project Manager?

What process aims to ensure accurate progress information is provided to the Project Manager?A . Starting up a ProjectB . Managing a Stage BoundaryC . Managing Product DeliveryD . Directing a ProjectView AnswerAnswer: C Explanation: The process that aims to ensure accurate progress information is provided to the Project Manager...

September 18, 2024No CommentsREAD MORE +

What product is used to maintain a record of those who have an interest in the project and their information requirements?

What product is used to maintain a record of those who have an interest in the project and their information requirements?A . Project PlanB . Communication Management StrategyC . Project BriefD . Project Product DescriptionView AnswerAnswer: B Explanation: The Communication Management Strategy is used in PRINCE2 to maintain a record...

September 18, 2024No CommentsREAD MORE +

Which is an objective of the Closing a Project process?

Which is an objective of the Closing a Project process?A . Review and approve the plan for project closureB . Review the performance of the project against its baselineC . Perform any post-project reviewsD . Create a Benefits Review PlanView AnswerAnswer: B Explanation: The objective of the Closing a Project...

September 18, 2024No CommentsREAD MORE +

Which product records any project outcomes perceived as negative by stakeholders?

Which product records any project outcomes perceived as negative by stakeholders?A . Business CaseB . Project PlanC . Communication Management StrategyD . Project Product DescriptionView AnswerAnswer: C Explanation: In PRINCE2®, the Communication Management Strategy is the document that outlines how project communications should be managed. It includes how information will...

September 18, 2024No CommentsREAD MORE +

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?A . Product DescriptionB . Team PlanC . Work PackageD . Stage PlanView AnswerAnswer: C Explanation: In PRINCE2®, a Work Package is the document where the Project Manager...

September 18, 2024No CommentsREAD MORE +