What first action should be taken?

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?A . Raise a request for changeB . Raise an off-specificationC . Write an Exception ReportD . Amend the Work PackageView AnswerAnswer: B Explanation: When a product cannot...

October 11, 2024 No Comments READ MORE +

Which is a true statement about time-driven controls?

Which is a true statement about time-driven controls?A . Time-driven controls are used for monitoring the progress of Work Packages and management stagesB . Time-driven controls take place when specific events happenC . Time-driven controls are produced at the end of a stageD . An Exception Report is a time-driven...

October 10, 2024 No Comments READ MORE +

Which is a difference between management and technical stages?

Which is a difference between management and technical stages?A . Management stages require planning and technical stages do notB . Technical stages can overlap and management stages cannotC . Management stages deliver products and technical stages do notD . Technical stages require resources and management stages do notView AnswerAnswer: B...

October 10, 2024 No Comments READ MORE +

Which is a task of product-based planning?

Which is a task of product-based planning?A . Identify activities and dependenciesB . Write the Project Product DescriptionC . Prepare the Work PackagesD . Produce Product Status AccountsView AnswerAnswer: B Explanation: A task of product-based planning in PRINCE2® is to write the Project Product Description. This is part of defining...

October 10, 2024 No Comments READ MORE +

Stakeholders may be internal or external to the corporate organization.

Stakeholders may be internal or external to the corporate organization.A . Only 1 is trueB . Only 2 is trueC . Both 1 and 2 are trueD . Neither 1 or 2 are trueView AnswerAnswer: C Explanation: Both statements about stakeholders are true in the context of PRINCE2®. A stakeholder...

October 9, 2024 No Comments READ MORE +

Which is NOT a purpose of the Organization theme?

Which is NOT a purpose of the Organization theme?A . Define a project management team structureB . Define the level of tolerance for each level of the project management teamC . Define the Project Board's responsibility for directing the projectD . Define which role is accountable for the project's successView...

October 9, 2024 No Comments READ MORE +

What is the first task of product-based planning?

What is the first task of product-based planning?A . Produce the Initiation Stage PlanB . Write the Project Product DescriptionC . Identify dependenciesD . Create the product breakdown structureView AnswerAnswer: B Explanation: The first task of product-based planning in PRINCE2 is to write the Project Product Description. This description defines...

October 9, 2024 No Comments READ MORE +

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

What theme provides all management levels within the project management team with mechanisms for monitoring and control?A . ProgressB . ChangeC . OrganizationD . QualityView AnswerAnswer: A Explanation: The Progress theme in PRINCE2 provides all management levels within the project management team with mechanisms for monitoring and control. It involves...

October 9, 2024 No Comments READ MORE +

Which does NOT reflect the PRINCE2 principle of continued business justification?

Which does NOT reflect the PRINCE2 principle of continued business justification?A . There must be a justifiable reason for starting a projectB . The business justification drives decision makingC . If a project is no longer forecast to deliver a financial benefit, it should be stopped.D . If a project...

October 9, 2024 No Comments READ MORE +

Which is NOT a purpose of the Initiating a Project process?

Which is NOT a purpose of the Initiating a Project process?A . Enable a Project Board decision about the commitment of resources to a projectB . Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approvedC . Establish...

October 8, 2024 No Comments READ MORE +