The Identify Stakeholders process is found in which Process Group?

The Identify Stakeholders process is found in which Process Group?A . InitiatingB . Monitoring and ControllingC . PlanningD . ExecutingView AnswerAnswer: A

February 23, 2020 No Comments READ MORE +

The process of prioritizing risks for further analysis or action is known as:

The process of prioritizing risks for further analysis or action is known as:A . Plan Risk Management.B . Plan Risk Responses.C . Perform Qualitative Risk Analysis.D . Perform Quantitative Risk Analysis.View AnswerAnswer: C

February 23, 2020 No Comments READ MORE +

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:A . Historical information and the lessons-learned database.B . Historical information and the stakeholder register.C . Organizational process assets and the lessons-learned database.D . Project documents and historical information.View AnswerAnswer: A

February 22, 2020 No Comments READ MORE +

Which project risk listed in the table below is most likely to occur?

Which project risk listed in the table below is most likely to occur? A . 1B . 2C . 3D . 4View AnswerAnswer: B

February 22, 2020 No Comments READ MORE +

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:A . appetiteB . toleranceC . thresholdD . managementView AnswerAnswer: B

February 21, 2020 No Comments READ MORE +

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:A . portfolioB . programC . selectionD . sub portfolioView AnswerAnswer: B

February 21, 2020 No Comments READ MORE +

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

A complete set of concepts, terms, and activities that make up an area of specialization is known as:A . a Knowledge AreaB . a Process GroupC . program managementD . portfolio managementView AnswerAnswer: A

February 21, 2020 No Comments READ MORE +

Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?A . Collect RequirementsB . Plan Scope ManagementC . Define ScopeD . Define ActivitiesView AnswerAnswer: A

February 20, 2020 No Comments READ MORE +

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?

Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?A . UniformB . ContinuousC . DiscreteD . LinearView AnswerAnswer: C

February 20, 2020 No Comments READ MORE +

Technical capability, past performance, and intellectual property rights are examples of:

Technical capability, past performance, and intellectual property rights are examples of:A . performance measurement criteriaB . source selection criteriaC . product acceptance criteriaD . phase exit criteriaView AnswerAnswer: B

February 20, 2020 No Comments READ MORE +