A tool and technique used in the Develop Project Charter process is:
A tool and technique used in the Develop Project Charter process is:A . change control toolsB . expert judgmentC . meetingsD . analytical techniquesView AnswerAnswer: B
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:A . ResponsesB . AppetiteC . ToleranceD . AttitudeView AnswerAnswer: A
Which input to the Plan Risk Management process provides information on high-level risks?
Which input to the Plan Risk Management process provides information on high-level risks?A . Project charterB . Enterprise environmental factorsC . Stakeholder registerD . Organizational process assetsView AnswerAnswer: A
Project Stakeholder Management focuses on:
Project Stakeholder Management focuses on:A . project staff assignmentsB . project tea m acquisitionC . managing conflicting interestsD . communication methodsView AnswerAnswer: C
Projects are undertaken by an organization to support the:
Projects are undertaken by an organization to support the:A . Product performance.B . Budget process.C . Collective capabilities.D . Organizational strategy.View AnswerAnswer: D
Which process is included in the Project Integration Management Knowledge Area?
Which process is included in the Project Integration Management Knowledge Area?A . Manage Project TeamB . Collect RequirementsC . Sequence ActivitiesD . Direct and Manage Project WorkView AnswerAnswer: D
The formal and informal interaction with others in an organization industry, or professional environment is known as:
The formal and informal interaction with others in an organization industry, or professional environment is known as:A . negotiationB . organizational theoryC . meetingD . networkingView AnswerAnswer: D
Which type of managers do composite organizations involve?
Which type of managers do composite organizations involve?A . Functional managers and manager of project managersB . Functional managers onlyC . Project managers onlyD . Technical managers and project managersView AnswerAnswer: C
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?A . Identify RisksB . Perform Qualitative Risk AnalysisC . Plan Risk ManagementD . Perform Quantitative Risk AnalysisView AnswerAnswer: B
The product scope description is used to:
The product scope description is used to:A . Gain stakeholders' support for the project.B . Progressively elaborate the characteristics of the product, service, or result.C . Describe the project in great detail.D . Define the process and criteria for accepting a completed product, service, or result.View AnswerAnswer: B