A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:A . ROI. B. SOW. C. RFI. D. RPRView AnswerAnswer: A Explanation: The output...

May 30, 2023 No Comments READ MORE +

Which of the following should be added to the issue log?

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?A . Continuous integration B. Rollback plan C. Customer notification D. Automated testingView AnswerAnswer: C Explanation: Customer notification...

May 30, 2023 No Comments READ MORE +

Which of the following is the BEST action for the project manager to take?

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?A . Exploit the risk. B. Accept the risk. C. Avoid the risk. D. Transfer the risk.View AnswerAnswer: A Explanation: The project manager should exploit the...

May 30, 2023 No Comments READ MORE +

Which of the following is the BEST action for the project manager to take?

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?A . Exploit the risk. B. Accept the risk. C. Avoid the risk. D. Transfer the risk.View AnswerAnswer: A Explanation: The project manager should exploit the...

May 2, 2023 No Comments READ MORE +

Which of the following should have been considered during initial planning to prevent this situation?

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have...

May 2, 2023 No Comments READ MORE +

Which of the following activities still needs to be performed to complete the schedule?

By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?A . Allocate resources. B. Determine...

May 1, 2023 No Comments READ MORE +

Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?

During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated...

April 30, 2023 No Comments READ MORE +

Which of the following is the NEXT step for the project manager?

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?A . Update the project charter. B. Determine budget constraints. C. Create a project schedule D. Validate the business case.View AnswerAnswer: A Explanation: Update the project charter. Updating...

April 29, 2023 No Comments READ MORE +

During a gate review meeting, the deliverable was rejected by the customer.

During a gate review meeting, the deliverable was rejected by the customer. INSTRUCTIONS Review the dashboard. * Part 1: Drag and drop each task, placing them in the correct order based on the project change control process. * Part 2: Select the proper document(s) to be updated. If at any...

April 29, 2023 No Comments READ MORE +

Which of the following can use the survey results as an input?

Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?A . Daily stand-up B. Project momentum C. Performance feedback D. Meeting minutesView AnswerAnswer: C Explanation:...

April 29, 2023 No Comments READ MORE +