Which of the following constraints are MOST likely to be affected?

A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved. Which of the...

October 8, 2018 No Comments READ MORE +

Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?A . Sales clerkB . Marketing representativeC . Team leadD . Product itemView AnswerAnswer: B

October 4, 2018 No Comments READ MORE +

Which of the following factors will MOST likely influence the communication methods used in the project?

A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable. Which of the following factors will MOST likely influence the communication methods used in the project?A . Personal preferencesB . Technological factorsC . Language...

September 30, 2018 No Comments READ MORE +

Which of the following conflict resolution techniques is the project manager using?

A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with...

September 29, 2018 No Comments READ MORE +

Which of the following describes a burn rate?

Which of the following describes a burn rate?A . The rate at which project documents are disposed.B . The rate at which project personnel leave the project.C . The rate at which the project budget is used.D . The rate at which the timeline increases.View AnswerAnswer: C Explanation: References: Kim...

September 28, 2018 No Comments READ MORE +

The PMO is responsible for: (Choose two.)

The PMO is responsible for: (Choose two.)A . managing the project plan, scope, risk, and budget.B . contributing expertise, deliverables, and estimates of costs.C . setting standards and practices for the organization and providing governance.D . outlining consequences of non-performance and coordinating between disparate projects.E . approving funding, developing the...

September 27, 2018 No Comments READ MORE +

Which of the following terms describe this requirement?

A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor. Which of the following terms describe this requirement?A . OutsourcingB . Business acquisitionC . Business process changeD . Internal...

September 21, 2018 No Comments READ MORE +

Which of the following is the MOST effective method for providing these updates?

A project requires daily status updates. Which of the following is the MOST effective method for providing these updates?A . BacklogB . StandupC . KickoffD . RetrospectiveView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306

September 18, 2018 No Comments READ MORE +

Which of the following are characteristics of a project? (Choose two.)

Which of the following are characteristics of a project? (Choose two.)A . OngoingB . TemporaryC . Start and finishD . Achieving a goalE . Consisting of milestonesF . Restricting the budgetView AnswerAnswer: BC Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 27

September 17, 2018 No Comments READ MORE +

Which of the following should the project manager do NEXT?

The project manager for a TV tower construction project receives notification that a strong storm is expected the following week. Which of the following should the project manager do NEXT?A . Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.B . Evaluate the risk,...

September 17, 2018 No Comments READ MORE +