Which of the following defines a group of projects that work together to achieve a common goal?

Which of the following defines a group of projects that work together to achieve a common goal?A . ProductB . PortfolioC . ProgramD . Project planView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 71

February 14, 2019 No Comments READ MORE +

In which of the following documents can this information be found?

A project manager needs to identify the resources assigned to a particular task. In which of the following documents can this information be found?A . Project scheduleB . Cost planC . Scope statementD . Impact assessmentView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis,...

February 11, 2019 No Comments READ MORE +

When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?

When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?A . Issue logB . Risk management planC . Communications planD . Risk registerE . Status reportView AnswerAnswer: D

February 7, 2019 No Comments READ MORE +

Which of the following should be tasked with ensuring resources are appropriately allocated to projects?

An organization has multiple projects that are taking place simultaneously. Which of the following should be tasked with ensuring resources are appropriately allocated to projects?A . PMOB . Project sponsorC . Project coordinatorD . HRView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017,...

February 3, 2019 No Comments READ MORE +

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?A . SCRUM retrospectiveB . Kickoff meetingC . Budget baselineD . Risk reviewView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306

February 2, 2019 No Comments READ MORE +

Which of the following is a definition of an RFP?

Which of the following is a definition of an RFP?A . A document sent to potential vendors to solicit a bid for a project.B . A document sent to potential vendors to request information for skills and experience for a project.C . A document sent to potential vendors to request...

January 25, 2019 No Comments READ MORE +

Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?A . SOWB . POC . SLAD . MOUView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299

January 25, 2019 No Comments READ MORE +

Which of the following documents should the project manager use to obtain this information?

A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints. Which of the following documents should the project manager use to obtain this information?A...

January 24, 2019 No Comments READ MORE +

Which of the following should the project manager do to obtain the resources?

The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources. Which of the following should the project manager do to obtain the resources?A . The project manager should identify and document the reasons for the additional resources in a...

January 21, 2019 No Comments READ MORE +

Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.

Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option. This type of conflict resolution is known as:A . forcing.B . avoiding.C . smoothing.D ....

January 15, 2019 No Comments READ MORE +