Which of the following meetings should be held to move to the NEXT step in the project?

The client accepts the critical design review. Which of the following meetings should be held to move to the NEXT step in the project?A . ExecutionB . KickoffC . ClosureD . PlanningView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 112

March 6, 2019 No Comments READ MORE +

Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?

Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?A . EACB . BACC . CPID . ETCView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231

March 6, 2019 No Comments READ MORE +

Which of the following describes how a project is related to a program?

Which of the following describes how a project is related to a program?A . A program is a combination of multiple projects.B . A program contains an element of the project.C . A program is a part of a project.D . A program uses half of the project’s budget.View AnswerAnswer:...

March 1, 2019 No Comments READ MORE +

Which of the following activities are associated with the closing phase of a project? (Choose two.)

Which of the following activities are associated with the closing phase of a project? (Choose two.)A . Risk mitigationB . Archiving of project documentsC . Tracking of expendituresD . Lessons learnedE . Quality assuranceView AnswerAnswer: BD Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p....

February 28, 2019 No Comments READ MORE +

Which of the following techniques is MOST likely to be used to complete the project on time?

A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time. Which of the following techniques is MOST likely to be used to complete the project on time?A . ThrottlingB . CrashingC . Resource...

February 26, 2019 No Comments READ MORE +

Which of the following would be the BEST source for the high-level project requirements?

A new project charter is being drafted. Which of the following would be the BEST source for the high-level project requirements?A . SponsorB . Project managerC . Project management officeD . Project teamView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 108

February 25, 2019 No Comments READ MORE +

Which of the following project documents should be used to record the occurrence of an unplanned event?

Which of the following project documents should be used to record the occurrence of an unplanned event?A . Action logB . Risk logC . Change logD . Issue logView AnswerAnswer: D Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 327

February 21, 2019 No Comments READ MORE +

Which of the following phases does this describe?

A project manager is working on the project charter. Which of the following phases does this describe?A . InitiationB . PlanningC . ExecutionD . ClosingView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107

February 20, 2019 No Comments READ MORE +

Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?

A critical stakeholder has requested additional status updated beyond the schedule. Which of the following factors MOST likely needs to be accounted for when communication with this stakeholder?A . ConfidentialityB . CriticalityC . FrequencyD . Cultural differencesView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,...

February 19, 2019 No Comments READ MORE +

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?A . 12 daysB . 14 daysC . 16 daysD . 19 daysView AnswerAnswer:...

February 18, 2019 No Comments READ MORE +