Which of the following is a schedule that illustrates the duration of an activity?
Which of the following is a schedule that illustrates the duration of an activity?A . Process diagramB . Ishikawa diagramC . Gantt chartD . Pareto chartView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 168
Which of the following is the MOST effective method for providing these updates?
A project requires daily status updates. Which of the following is the MOST effective method for providing these updates?A . BacklogB . StandupC . KickoffD . RetrospectiveView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306
Which of the following describes a burn rate?
Which of the following describes a burn rate?A . The rate at which project documents are disposed.B . The rate at which project personnel leave the project.C . The rate at which the project budget is used.D . The rate at which the timeline increases.View AnswerAnswer: C Explanation: References: Kim...
Which of the following tasks are on the critical path?
There are four parallel paths on a network diagram. The summary duration of each path is below: A, C, G: 10 weeks A, B, F: 8 weeks D, E, H: 12 weeks D, B, F: 7 weeks Which of the following tasks are on the critical path?A . A, C,...
Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?
Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?A . Sales clerkB . Marketing representativeC . Team leadD . Product itemView AnswerAnswer: B
Which of the following would the project manager MOST likely do?
A project team member highlights to the project manager that expensive licensing for critical software in use across the project may expire before the completion project. Which of the following would the project manager MOST likely do?A . Place a risk on the risk register and arrange a risk review...
Which of the following are examples of organizational change? (Choose two.)
Which of the following are examples of organizational change? (Choose two.)A . RelocationB . ScopeC . Business processD . ScheduleE . Risk eventView AnswerAnswer: A,C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297
Which of the following documents should be used to provide high-level reporting to key stakeholders?
Which of the following documents should be used to provide high-level reporting to key stakeholders?A . DashboardB . Communication planC . Statement of workD . Project charterView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 325
Which of the following factors will MOST likely influence the communication methods used in the project?
A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable. Which of the following factors will MOST likely influence the communication methods used in the project?A . Personal preferencesB . Technological factorsC . Language...
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?
Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?A . EACB . BACC . CPID . ETCView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231