Which of the following should the project manager do to resolve this issue?
A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following should the project manager do to resolve this issue?A . Update the scope management plan.B . Modify the project baselines.C...
Which of the following activities are associated with the closing phase of a project? (Choose two.)
Which of the following activities are associated with the closing phase of a project? (Choose two.)A . Risk mitigationB . Archiving of project documentsC . Tracking of expendituresD . Lessons learnedE . Quality assuranceView AnswerAnswer: B,D Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p....
Which of the following is MOST likely to be the main challenge the influences this decision?
A project manager who is part of a global team wants to have a team building meeting and decides to hold a video conference. Which of the following is MOST likely to be the main challenge the influences this decision?A . Geographical factorsB . Language barriersC . Cultural differencesD ....
Which of the following should the project manager do NEXT?
A project in the execution phase is over budget, and tasks on the critical path are on schedule. Which of the following should the project manager do NEXT?A . Update the project management plan.B . Issue a change request.C . Revise the project charter.D . Evaluate the impact to the...
Which of the following meetings should be held to move to the NEXT step in the project?
The client accepts the critical design review. Which of the following meetings should be held to move to the NEXT step in the project?A . ExecutionB . KickoffC . ClosureD . PlanningView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 112
Which of the following items should the project manager use to highlight the vendor’s areas of poor performance?
The project manager has noticed a vendor is not performing in accordance with the SLA. Which of the following items should the project manager use to highlight the vendor’s areas of poor performance? A. Balanced score card B. WBS C. Post-project evaluation D. PERTView AnswerAnswer: A Explanation: References: Kim Heldman,...
Which of the following information should the project manager provide?
Maintenance estimates. Which of the following information should the project manager provide?A . Cost baselineB . Burn rateC . Cost variance reportD . Total project costView AnswerAnswer: A
Which of the following should the project manager do to obtain the resources?
The project sponsor has cut the resources required for project completion. The project manager cannot complete the project without additional resources. Which of the following should the project manager do to obtain the resources?A . The project manager should identify and document the reasons for the additional resources in a...
Which of the following is the primary purpose of an MOA or an MOU?
Which of the following is the primary purpose of an MOA or an MOU?A . State expectations of all signatory parties to reduce potential misunderstandings.B . Facilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.C . Enumerate a detailed code of conduct for...
Which of the following conflict resolution techniques is the project manager using?
A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with...