Which of the following effects is this MOST likely to have on the project?
A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority. Which of the following effects is this MOST...
Which of the following documents should the project manager use to obtain this information?
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints. Which of the following documents should the project manager use to obtain this information?A...
Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?
Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?A . SOWB . POC . SLAD . MOUView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299
Which of the following documents should the project manager create?
A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries. Which of the following documents should the project manager create?A...
Which of the following is the NEXT step?
A project manager is justifying a required change with the associated impact on the project. Which of the following is the NEXT step?A . ImplementationB . ApprovalC . ValidationD . AuditingView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294
Which of the following steps should take place NEXT?
A customer has requested additional features for an active project. Which of the following steps should take place NEXT?A . Implement the requested changes.B . Evaluate the impact of the changes.C . Update all project documents.D . Submit the requested changes to the CCView AnswerAnswer: B Explanation: References: Kim Heldman,...
Which of the following is a necessary step to record the actual durations?
A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?A . Establish each WBS work package resource.B . Establish and set the baseline.C . Establish and set the...
Which of the following describes how the project manager should BEST determine the initial sequence and durations?
After identifying all known tasks, the project manager has started to sequence and set durations. Which of the following describes how the project manager should BEST determine the initial sequence and durations?A . Use milestones identified in the project charter.B . Use data based on past knowledge.C . Hold a...
Which of the following techniques is MOST likely to be used to complete the project on time?
A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time. Which of the following techniques is MOST likely to be used to complete the project on time?A . ThrottlingB . CrashingC . Resource...
Which of the following is a key aspect of the Agile project management methodology?
Which of the following is a key aspect of the Agile project management methodology?A . Test-drivenB . Daily standup meetingsC . Short project durationsD . Defined list of requirementsView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 286