Which of the following documents will the company MOST likely release FIRST?

A company has determined it does not have the in-house capability to perform a project and wants to procure third-party services. Which of the following documents will the company MOST likely release FIRST?A . RFOB . RFIC . RFPD . RFQView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study...

October 30, 2019 No Comments READ MORE +

Which of the following is a characteristics of a matrix organization?

Which of the following is a characteristics of a matrix organization?A . Authority lies solely with the project manager.B . Authority is directed by the project architect.C . Authority is shared between the project manager and project coordinator.D . Authority is shared between functional and project managers.View AnswerAnswer: D Explanation:...

October 30, 2019 No Comments READ MORE +

Which of the following are characteristics of a project? (Choose two.)

Which of the following are characteristics of a project? (Choose two.)A . OngoingB . TemporaryC . Start and finishD . Achieving a goalE . Consisting of milestonesF . Restricting the budgetView AnswerAnswer: B,C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 27

October 29, 2019 No Comments READ MORE +

Which of the following factors MOST likely needs to be accounted for when communicating with this stakeholder?

A critical stakeholder has requested additional status updated beyond the schedule. Which of the following factors MOST likely needs to be accounted for when communicating with this stakeholder?A . ConfidentialityB . CriticalityC . FrequencyD . Cultural differencesView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex,...

October 29, 2019 No Comments READ MORE +

When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?

A project team is comprised of a mix of in-house and virtual team members. When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?A . Composing a project team email with the details of the...

October 28, 2019 No Comments READ MORE +

Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes?

A stakeholder is unaware of a project’s status. Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)A . Status reportB . Organizational chartC . RACI matrixD . Meeting minutesE . Communication planView AnswerAnswer: A,D Explanation: References: Kim Heldman,...

October 28, 2019 No Comments READ MORE +

The PMO is responsible for: (Choose two.)

The PMO is responsible for: (Choose two.)A . managing the project plan, scope, risk, and budget.B . contributing expertise, deliverables, and estimates of costs.C . setting standards and practices for the organization and providing governance.D . outlining consequences of non-performance and coordinating between disparate projects.E . approving funding, developing the...

October 28, 2019 No Comments READ MORE +

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?A . 12 daysB . 14 daysC . 16 daysD . 19 daysView AnswerAnswer:...

October 28, 2019 No Comments READ MORE +

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?A . SCRUM retrospectiveB . Kickoff meetingC . Budget baselineD . Risk reviewView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306

October 27, 2019 No Comments READ MORE +

Which of the following should the project manager do NEXT?

A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager do NEXT?A . Gain approval for the changes.B . Identify the approval authority.C . Implement the changes.D . Create an...