Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option. This type of conflict resolution is known as:A . forcing.B . avoiding.C . smoothing.D ....
Which of the following describes how the project manager should BEST determine the initial sequence and durations?
After identifying all known tasks, the project manager has started to sequence and set durations. Which of the following describes how the project manager should BEST determine the initial sequence and durations?A . Use milestones identified in the project charter.B . Use data based on past knowledge.C . Hold a...
Which of the following is the primary purpose of an MOA or an MOU?
Which of the following is the primary purpose of an MOA or an MOU?A . State expectations of all signatory parties to reduce potential misunderstandings.B . Facilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.C . Enumerate a detailed code of conduct for...
Which of the following should a project manager update to document this information?
A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave. Which of the following should a project...
To alter the pace of the project, which of the following should the project manager do FIRST?
The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date. To alter the pace of the...
Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?
Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?A . Sales clerkB . Marketing representativeC . Team leadD . Product itemView AnswerAnswer: B
Which of the following project documents should be used to record the occurrence of an unplanned event?
Which of the following project documents should be used to record the occurrence of an unplanned event?A . Action logB . Risk logC . Change logD . Issue logView AnswerAnswer: D Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 327
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
A WBS is being developed for a project. Which of the following would be BEST suited to contribute cost and time estimates for the project activities?A . Project team membersB . Project sponsorC . Project managerD . Project schedulerView AnswerAnswer: B Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd...
Which of the following documents should the project manager use to obtain this information?
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints. Which of the following documents should the project manager use to obtain this information?A...
This action is known as which of the following?
A business has implemented a new online performance management tool that allows functional and project managers to rate employees online. This action is known as which of the following?A . Business process changeB . Organizational changeC . Internal reorganizationD . Business continuity planningView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA...