Which of the following make up a company’s portfolio? (Choose two.)

Which of the following make up a company’s portfolio? (Choose two.)A . PeopleB . ProceduresC . ProjectsD . ProcessesE . ProfitF . ProgramsView AnswerAnswer: C,F

June 4, 2021 No Comments READ MORE +

Which of the following describes how a project is related to a program?

Which of the following describes how a project is related to a program?A . A program is a combination of multiple projects.B . A program contains an element of the project.C . A program is a part of a project.D . A program uses half of the project’s budget.View AnswerAnswer:...

June 3, 2021 No Comments READ MORE +

Which of the following shows projected project expenditures?

Which of the following shows projected project expenditures?A . Work breakdown structureB . Cash flow scheduleC . Cash burn rateD . Budget milestoneView AnswerAnswer: A

June 3, 2021 No Comments READ MORE +

Which of the following BEST describes these projects?

A company has completed its annual strategic planning session. As a result, several related projects, which will achieve the company’s technological improvement goals, are identified . Which of the following BEST describes these projects?A . PortfolioB . ProgramC . DeliverableD . OutcomeView AnswerAnswer: B

June 3, 2021 No Comments READ MORE +

Which of the following changes would BEST satisfy the project sponsor?

The internal project sponsor is frustrated by a lack of concise, regular updates regarding the status of a project. Which of the following changes would BEST satisfy the project sponsor?A . Add the project sponsor to all project email correspondence moving forwardB . Include the project sponsor in all project...

June 3, 2021 No Comments READ MORE +

Which of the following will allow the project team to ensure all deliverables are included in the final product while managing scope creep?

A client has provided a list of deliverables to include in the project scope . Which of the following will allow the project team to ensure all deliverables are included in the final product while managing scope creep?A . Requirements traceability matrixB . Gantt chartC . SWOT analysisD . Project...

June 3, 2021 No Comments READ MORE +

Which of the following should be used to complete the tasks on time?

A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern . Which of the following should be used to complete the tasks on time?A . Fast-track the tasks.B . Utilize positive float.C . Crash the schedule.D . Remove...

June 3, 2021 No Comments READ MORE +

Which of the following is a risk strategy?

Which of the following is a risk strategy?A . Risk quantificationB . Risk avoidanceC . Risk identificationD . Risk reviewView AnswerAnswer: B

June 3, 2021 No Comments READ MORE +

A local company is part of a hostile takeover by a multinational conglomerate. The Chief Executive Officer ( CEO) directs that all meetings be conducted via video conference to save costs and expedite communication.

A local company is part of a hostile takeover by a multinational conglomerate. The Chief Executive Officer ( CEO) directs that all meetings be conducted via video conference to save costs and expedite communication. This scenario is an example of:A . outsourcing.B . corporate acquisition.C . internal reorganization.D . process...

June 3, 2021 No Comments READ MORE +

Which of the following inherently affects quality standards?

Which of the following inherently affects quality standards?A . SLAB . MOAC . MOUD . WBSView AnswerAnswer: D

June 3, 2021 No Comments READ MORE +