Which of the following resources has the authority to authorize this change?
A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling. Which of the following resources has the authority to authorize this change?A . StakeholdersB . Scrum...
Which of the following risk strategies is represented by the purchase of insurance?
Which of the following risk strategies is represented by the purchase of insurance?A . MitigateB . AcceptC . TransferD . AvoidView AnswerAnswer: C Explanation: Explanation “Transfer: Moving the liability for the risk to a third party by purchasing insurance, performance bonds, and so on”
Which of the following is used to perform a root cause analysis?
Which of the following is used to perform a root cause analysis?A . Ishikawa diagramB . Bar chartC . Pareto diagramD . Scatter plotView AnswerAnswer: A Explanation: Reference http://asq.org/learn-about-quality/cause-analysis-tools/overview/overview.html
Which of the following primary factors are used to prioritize the development of risk response strategies? ( Choose two.)
Which of the following primary factors are used to prioritize the development of risk response strategies? ( Choose two.)A . LikelihoodB . TimelineC . ImpactD . QualityE . CostView AnswerAnswer: A,C
Which of the following charts should the PM include in the status report?
The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project . Which of the following charts should the PM include in the status report?A . Gantt chartB . Scatter chartC . Run chartD . Process diagramView AnswerAnswer:...
Which of the following describes the difference between an acquisition and outsourcing?
Which of the following describes the difference between an acquisition and outsourcing?A . In an acquisition, the organizations remain separate, whereas they become one in outsourcing.B . In an acquisition, the organizations become one, whereas they move to a new location in outsourcing.C . In an acquisition, the organizations become...
Which of the following information does the project risk register typically contain?
Which of the following information does the project risk register typically contain?A . Type of risk, identified risk, risk response, impact of risk, severity of riskB . Type of risk, project task, risk response, impact of risk, severity of riskC . Type of risk, identified risk, risk response, project schedule...
Which of the following types of procurement should be used?
An organization needs a vendor to provide a solution. The organization can only describe its goals but not how to accomplish the work. Which of the following types of procurement should be used?A . Request for informationB . Request for quoteC . Request for bidD . Request for proposalView AnswerAnswer:...
Which of the following is a reason for assessing risk in a project?
Which of the following is a reason for assessing risk in a project?A . To identify new tasksB . To shorten the project timelineC . To avoid reworkD . To establish a budgetView AnswerAnswer: C
Which of the following ways should the project manager update the risk register?
Risk ID 2 has occurred. Which of the following ways should the project manager update the risk register?A . Add a column for probability and set risk 2 at 100%B . Change the risk 2 response to backups restoredC . Change the risk 2 status to issueD . Change the...