Which of the following correctly defines the organization in program management terminology?

A wild life protection organization opposes your program, which involves the cutting of around 200 trees to make way for the construction of a building. Which of the following correctly defines the organization in program management terminology?A . Negative stakeholderB . Positive stakeholderC . Key stakeholderD . Hurdle stakeholderView AnswerAnswer:...

June 20, 2021 No Comments READ MORE +

Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?A . Fast trackingB . CompressingC . FloatD . CrashingView AnswerAnswer: A

June 20, 2021 No Comments READ MORE +

What program selection method is management using in this instance?

Management is trying to determine which program to initiate. Each of the potential programs has the possibility of creating an income for each it is in existence. Management would like to consider the present value for each year a program creates a return on investment. What program selection method is...

June 20, 2021 No Comments READ MORE +

The outsourcing of the dangerous work to a specialist is what type of risk response?

You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you've decided is too risky for the program team members so you've hired specialists to manage the dangerous work...

June 20, 2021 No Comments READ MORE +

What activity should the program manager perform next?

A program is developing a next-generation product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet. What activity should the program manager perform next?A . Program delivery managementB . Resource interdependency managementC . Program performance monitoring and controllingD . Benefits...

June 19, 2021 No Comments READ MORE +

schedule. Based on this information, what is the schedule performance index (SPI) for this program?

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years . The program is currently 30 percent complete and you have spent $789,000 . The program is supposed to be 35 percent complete but do...

June 19, 2021 No Comments READ MORE +

What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?

Robert's program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?A . Lead timeB...

June 19, 2021 No Comments READ MORE +

How should the program manager demonstrate the program's progress?

A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives. How should the program manager demonstrate the program's progress?A . Define the key performance indicators (KPIs) for the program's outcome.B . Invite the key stakeholder to review the...

June 19, 2021 No Comments READ MORE +

What action should the program manager take to realign the program?

The program manager takes over a poorly performing program. After a review of the documentation and interviews with the program sponsor, stakeholders, and program constituents, the program manager realizes that the program is not aligned with the corporate/organizational goals . The program manager must realign the constituent projects and components...

June 19, 2021 No Comments READ MORE +

What role do you play in Tom's project closure?

You are the program manager of the JNH Program. Tom, a project manager in your program, has just completed his project and is ready to officially close his project. You agree that Tom's project is completed. What role do you play in Tom's project closure?A . You must ensure that...

June 19, 2021 No Comments READ MORE +