What should the program manager do next?
The program manager has a global program with five component projects . The program sponsor wants the management plans, processes/procedures, and technology to be uniform across the program. The requirements will create issues and result in increased costs. The program sponsor is new and has imposed these new requirements six...
What should the program manager do next?
After attending a technology exposition, an influential stakeholder believes that integrating a new technology into the program will increase benefits and help shorten the schedule . The stakeholder asks the program manager to immediately include the new technology into the program. What should the program manager do next?A . Assess...
What should the program manager do to ensure a successful transition?
A small, regional utility closes a customer rewards program and transitions it to operations . The executive sponsor and program manager are concerned about the impact on benefits realization. The program manager assures the executive sponsor that any corrective actions will be included in the next phase. What should the...
What benefits would structuring work into programs bring to this organization?
A rapidly expanding IT company wants to mature its delivery methodology. It creates a benefits management plan that identifies formal program management governance as a key area that would add value. What benefits would structuring work into programs bring to this organization?A . Delivery of initiatives and objectives through the...
What should the regional program manager do to address the country manager’s request?
A newly appointed country manager suggests that the regional program manager use a social media platform to expedite communications and address questions. The new country manager used this social media platform at a previous job. What should the regional program manager do to address the country manager’s request?A . Suggest...
You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?
You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?A . Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the...
What does RACI stand for?
What does RACI stand for?A . Responsible, Account, Confirm, InformB . Responsible, Accountable, Consult, InformC . Roles, Accountable, Confirm, InformD . Roles, Action, Consult, InformView AnswerAnswer: B
Which document will be created to support this activity?
A program manager needs to establish direction and identify the essential aspects of a program. In addition, they must ensure that the context and framework of the program are properly defined, assessed, and documented. Which document will be created to support this activity?A . Program resource management planB . Program...
What does CPI value less than 1.0 indicates?
What does CPI value less than 1.0 indicates?A . Cost overrun for work completedB . Scheduled performance is greatC . Cost underrun of performance to dateD . Cost for completed work is as per estimateView AnswerAnswer: D
What is the minimum future value this organization should expect to receive from this program if it is initiated and the rate of return is six percent?
An organization is considering a new program . The program has a cost of $1,950,000 and will last for three years. What is the minimum future value this organization should expect to receive from this program if it is initiated and the rate of return is six percent?A . $2,322,481B...