What action should the program manager take to realign the program?
The program manager takes over a poorly performing program. After a review of the documentation and interviews with the program sponsor, stakeholders, and program constituents, the program manager realizes that the program is not aligned with the corporate/organizational goals . The program manager must realign the constituent projects and components...
Which of the following correctly defines the organization in program management terminology?
A wild life protection organization opposes your program, which involves the cutting of around 200 trees to make way for the construction of a building. Which of the following correctly defines the organization in program management terminology?A . Negative stakeholderB . Positive stakeholderC . Key stakeholderD . Hurdle stakeholderView AnswerAnswer:...
What program management process identifies the program sponsor?
You are the program manager for your organization. You're currently creating an accountability matrix starting with yourself, the program manager and the program sponsor. What program management process identifies the program sponsor?A . Pre-program setup phaseB . Authorization of program processes and projectsC . Initiate program processD . Initiation of...
What should the program manager do first?
A key stakeholder’s requirement contradicts the organization’s strategic objectives . The program manager meets with the stakeholder, but is unable to reach a compromise on the requirement. What should the program manager do first?A . Meet with the program management office to update the benefits management planB . Meet with...
Which of the following documents sets the project objectives?
Which of the following documents sets the project objectives?A . Project charterB . Project scheduleC . Project scope statementD . Project organization chartView AnswerAnswer: C
If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?
If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?A . .99B . -$2,500C . $2,500D . 1.02View AnswerAnswer: C
Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?
You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance. Which earned value management formula can you use to predict how...
Which of the following documents is described in the statement below?
Which of the following documents is described in the statement below? "It is a type of procurement document used to request proposals from prospective sellers of products or services."A . Request for informationB . Request for quoteC . Request for proposalD . Request for bidView AnswerAnswer: C
What is the other name for critical delivery dates?
What is the other name for critical delivery dates?A . Substantial completion.B . Phases.C . Flags.D . Milestones.View AnswerAnswer: D
What term is assigned to the actions that Andy is trying to do in this instance?
Andy is the program manager of the HQN Program. This program is nearing its completion and there is still $25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but...