The intent of waste management in the Materials and Resources credit category is to
The intent of waste management in the Materials and Resources credit category is toA . specify the use of green materialsB . promote the use of rapidly renewable resourcesC . reduce the amount of waste and toxins hauled to landfillsD . increase the use of pre-consumer/post-consumer recycled contentView AnswerAnswer: C
What is the current standard LEED uses to determine the baseline for indoor water savings?
What is the current standard LEED uses to determine the baseline for indoor water savings?A . Energy Policy Act (EPACT) of 1992. 2005B . ANSI 17024C . The local standard in which the project is locatedD . The Energy Savings and Industrial Competitiveness Act of 2013View AnswerAnswer: A
Energy and Atmosphere Credit encompasses
Energy and Atmosphere Credit encompassesA . site selection, site design and environmental concernsB . integrative process, building loads and EQC . building loads, energy performance management and EQD . building loads, energy performance management and environmental concernsView AnswerAnswer: C
Which of the following project characteristics demonstrate smart growth principles?
Which of the following project characteristics demonstrate smart growth principles?A . The project is built on a former chemical landfill siteB . The project consists of a sprawling new housing complex 5 mi. (8 km) from the nearest cityC . The project consists of two adult care facilities, three senior...
Open grid pavement tends to reduce
Open grid pavement tends to reduceA . native habitatB . heat island effectsC . rainwater infiltrationD . parking space requirementsView AnswerAnswer: B
Which industry benchmarking tool is used for measuring ongoing energy performance?
Which industry benchmarking tool is used for measuring ongoing energy performance?A . Bright Power's EnergyScoreCardB . U.S. Department of Energy's EnerCopC . EPA's ENERGY STAR Portfolio ManagerD . U.S. Department of Energy's EnergyIQView AnswerAnswer: C
Which of the following principles is a part of the integrated process?
Which of the following principles is a part of the integrated process?A . Cradle-to-cradleB . Systems thinkingC . Project schedulingD . Building information modelingView AnswerAnswer: B
In the commercial LEED rating systems, which point range will achieve the Silver level of certification?
In the commercial LEED rating systems, which point range will achieve the Silver level of certification?A . 30-39 pointsB . 40-49 pointsC . 50-59 pointsD . 60-69 pointsView AnswerAnswer: C
Green Building Council (USGBC) terminology for a LEED project?
Which of the following is an appropriate usage of U.S. Green Building Council (USGBC) terminology for a LEED project?A . LEED certified buildingB . LEED's certified buildingC . LEED Accredited BuildingD . LEED Registered, Gold BuildingView AnswerAnswer: A
During which stage of a project is implementation of the Integrative Process most effective in improving performance?
During which stage of a project is implementation of the Integrative Process most effective in improving performance?A . OperationB . Early de signC . ConstructionD . Construction documentView AnswerAnswer: B