Discussing the project goals to help identify the credits and options that the team should attempt is an example of

Discussing the project goals to help identify the credits and options that the team should attempt is an example ofA . documenting LEED creditsB . creating the Basis of Design (BOD)C . developing the LEED ScorecardD . implementing the Commissioning (Cx) PlanView AnswerAnswer: C Explanation: Discussing the project goals to...

March 16, 2024 No Comments READ MORE +

In a large industrial or commercial building, which energy end uses are classified as systems composed of discrete pieces of equipment that can be metered together for the purposes of Energy and Atmosphere Credit, Advanced Energy Metering?

In a large industrial or commercial building, which energy end uses are classified as systems composed of discrete pieces of equipment that can be metered together for the purposes of Energy and Atmosphere Credit, Advanced Energy Metering?A . HVAC air system for air conditioningB . Electrical lighting system during peak...

March 15, 2024 No Comments READ MORE +

At the time of registering a project in LEED Online, Regional Priority credits are determined based upon the project's

At the time of registering a project in LEED Online, Regional Priority credits are determined based upon the project'sA . environmental zoneB . longitude and latitudeC . ASHRAE 90.1 - 2010 climate zoneD . Environmental Protection Agency Phase I AssessmentView AnswerAnswer: B Explanation: At the time of registering a project...

March 15, 2024 No Comments READ MORE +

Which of the following actions should be the project team's top priority in order to demonstrate the minimum requirements to achieve Materials and Resources Prerequisite, Storage and Collection of Recyclables?

Based on the results of a six-hour waste stream study, the project team for a retail project plans to provide dedicated areas for four easily recyclable waste streams: cardboard, plastic, metal and paper. The project is open to the public 10 hours a day, six days a week. Which of...

March 15, 2024 No Comments READ MORE +

This strategy is an example of applying which of the following credits to the project?

During the early stages of a LEED for Schools project, the team was able to reduce the number of lighting fixtures in classrooms by 25% because the project team selected paint color whose light reflectance value was 75% instead of the initially proposed 64% value. This strategy is an example...

March 15, 2024 No Comments READ MORE +

Which of the following strategies will aid in reducing indoor water use?

Which of the following strategies will aid in reducing indoor water use?A . Design drip irrigation for landscapeB . Use high-efficiency HVAC systemsC . Exclude janitor closets in the buildingD . Optimize consumption of showerheadsView AnswerAnswer: D Explanation: According to the LEED v4: Building Design + Construction Guide, one of...

March 15, 2024 No Comments READ MORE +

A newly constructed school has installed solar thermal systems and wind turbines on site. To achieve the maximum number of Energy and Atmosphere points, which team members must be included?

A newly constructed school has installed solar thermal systems and wind turbines on site. To achieve the maximum number of Energy and Atmosphere points, which team members must be included?A . Energy Modeler and ContractorB . Construction Manager and Energy ModelerC . Energy Modeler and Commissioning (Cx) AgentD . Commissioning...

March 14, 2024 No Comments READ MORE +

Which of the following products must always be included in Materials and Resources credits?

Which of the following products must always be included in Materials and Resources credits?A . FaucetsB . FurnitureC . Interior PaintD . Fire suppression systemView AnswerAnswer: C Explanation: Interior paint must always be included in Materials and Resources credits. This is because interior paint is considered as a permanently installed...

March 14, 2024 No Comments READ MORE +

What are the three phases within the Integrative Process Credit, Integrative Process?

What are the three phases within the Integrative Process Credit, Integrative Process?A . Pre-design, Discovery, Design and ConstructionB . Discovery, Design and Construction, Operations and FeedbackC . Schematic Design, Design and Construction, Operations and FeedbackD . Design Charrette, Schematic Design, Operations and FeedbackView AnswerAnswer: A Explanation: The Integrative Process credit...

March 14, 2024 No Comments READ MORE +

Who must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

Who must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?A . The general contractorB . A LEED APC . The project's mechanical engineerD . The owner or an owner's representativeView AnswerAnswer: D Explanation: According to the LEED v4: Building Design...

March 14, 2024 No Comments READ MORE +