To achieve the maximum number of Energy and Atmosphere points, which team members must be included?
A newly constructed school has installed solar thermal systems and wind turbines on site. To achieve the maximum number of Energy and Atmosphere points, which team members must be included?A . Energy Modeler and ContractorB . Construction Manager and Energy ModelerC . Energy Modeler and Commissioning (Cx) AgentD . Commissioning...
The maximum number of points for Water Efficiency Credit, Cooling Tower Water Use can be obtained by
The maximum number of points for Water Efficiency Credit, Cooling Tower Water Use can be obtained byA . utilizing a once-through system without recirculationB . limiting cooling tower make-up to 50% of a potable sourceC . conducting a one-time potable water analysis to determine acceptable non-potable sourcesD . achieving a...
Selecting a high-reflectance interior paint which is compliant with South Coast Air Quality Management District (SCAQMD) Rule 1113 can help contribute towards which two credits?
Selecting a high-reflectance interior paint which is compliant with South Coast Air Quality Management District (SCAQMD) Rule 1113 can help contribute towards which two credits?A . Indoor Environmental Quality Credit, Low-Emitting Materials and Indoor Environmental Quality Credit, Interior LightingB . Indoor Environmental Quality Credit, Low-Emitting Materials and Sustainable Sites Credit,...
What stage of LEED for Neighborhood Development certification listed below is eligible for points under Building Design and Construction: New Construction, Location and Transportation Credit, LEED for Neighborhood Development Location?
What stage of LEED for Neighborhood Development certification listed below is eligible for points under Building Design and Construction: New Construction, Location and Transportation Credit, LEED for Neighborhood Development Location?A . LEED v4, LEED for Neighborhood Development Conditional ApprovalB . LEED for Neighborhood Development Pilot, Stage 3 LEED for Neighborhood...
A Healthcare Project is constructing a new building adjacent to an existing LEED Certified hospital facility. The new building's location is on the same hospital campus as the certified facility. The entire hospital campus was analyzed with an Environmental Site Assessment (ESA) as part of the certified facility's project scope. The new building project needs to complete a new Phase I ESA if
A Healthcare Project is constructing a new building adjacent to an existing LEED Certified hospital facility. The new building's location is on the same hospital campus as the certified facility. The entire hospital campus was analyzed with an Environmental Site Assessment (ESA) as part of the certified facility's project scope....
Which rating system is appropriate for a new mixed-use building with 300,000 ft2 (27 871 m2) of residential units, 150,000 ft2 (13 935 m2) hotel and 50,000 ft2 (4 645 m2) of retail space?
Which rating system is appropriate for a new mixed-use building with 300,000 ft2 (27 871 m2) of residential units, 150,000 ft2 (13 935 m2) hotel and 50,000 ft2 (4 645 m2) of retail space?A . RetailB . HospitalityC . Core and Shell DevelopmentD . New ConstructionView AnswerAnswer: D Explanation: New...
Which of the following contributes to the value of the commissioning process?
Which of the following contributes to the value of the commissioning process?A . Ensuring that the project budgetary goal is metB . Verifying that the building systems perform as intendedC . Verifying that the building water fixtures are installed properlyD . Ensuring that the project is delivered to meet the...
Which of the following innovation proposals is most likely to be successful to achieve an Innovation Credit?
Which of the following innovation proposals is most likely to be successful to achieve an Innovation Credit?A . Providing an educational program on the environmental and human health benefits of green building practicesB . Including locked, indoor bicycle storage for 100% of project occupantsC . Being located next to a...
Which of the following strategies would be considered an acceptable minor improvement within the wetland buffer for Location and Transportation Credit, Sensitive Land Protection?
Which of the following strategies would be considered an acceptable minor improvement within the wetland buffer for Location and Transportation Credit, Sensitive Land Protection?A . Build a two-story fitness facilityB . Change the grade to install a security fenceC . Provide a vehicular access drive that is less than 16...
What phase of the integrative process gives the team the greatest chance of success in meeting the project's environmental goals cost-effectively?
What phase of the integrative process gives the team the greatest chance of success in meeting the project's environmental goals cost-effectively?A . DesignB . DiscoveryC . OperationsD . ConstructionView AnswerAnswer: B Explanation: . Discovery The discovery phase of the integrative process gives the team the greatest chance of success in...