How many P2P leaf-to-spine addresses are there?
In your design, you have six racks each with a pair of VSX Leaf switches and two Spine switches. How many P2P leaf-to-spine addresses are there?A . 12B . 96C . 24D . 48View AnswerAnswer: D
What does a five-nines requirement in a service agreement refer to?
What does a five-nines requirement in a service agreement refer to?A . Compliance with a particular section of PCI DSSB . Unplanned downtime less than .001% of the service termC . Five layers of redundancy in the network designD . Future-proof solution designed to last five or more yearsView AnswerAnswer:...
Mention two disadvantages of the End-of-Row or Middle-of-Row switches in Data Center design
Mention two disadvantages of the End-of-Row or Middle-of-Row switches in Data Center designA . More equipmentB . Higher latency for rack-to-rack traffic within the rowC . Longer, more complex cabling within the rowD . Lower port density and less scalableView AnswerAnswer: C, D
What can be used to encrypt data in flight between untrusted locations?
What can be used to encrypt data in flight between untrusted locations?A . OSPF authenticationB . MACSecC . GRE tunnelsD . MD5 encryptionView AnswerAnswer: B
What is the transit VLAN that runs between VSX members?
What is the transit VLAN that runs between VSX members?A . Must not be assigned IP addresses on any switch.B . It is used as a keepAlive mechanismC . It is a routed VLAN allowed in the ISL to ensure that the two switches within a VSX pair can learn...
In Aruba CX 10000 switches, how many SFP28 port-groups are there?
In Aruba CX 10000 switches, how many SFP28 port-groups are there?A . Twelve port-groups with four ports eachB . Four port-groups with twelve ports eachC . No port-groupsD . One port-group that has all the portsView AnswerAnswer: A
What is the maximum distance supported by this setup?
In MMF OM3 fiber type and SFP28 LC SR transceiver option. What is the maximum distance supported by this setup?A . Up to 50 metersB . Up to 70 metersC . Up to 500 metersD . Up to 700 metersView AnswerAnswer: B
In Aruba CX 8325 switches, what is true about port-groups?
In Aruba CX 8325 switches, what is true about port-groups?A . Can have transceivers that operate at 100 GbpsB . Each port-group can have different speed transceiversC . All port-groups transceivers need to be of the same speedD . Must have the same speed transceivers within a port-groupView AnswerAnswer: D
In L3 Spine and Leaf design, which answer is correct?
In L3 Spine and Leaf design, which answer is correct?A . Leaf switches connect to other leaf switchesB . Each leaf switch connects to each spine switchC . Each spine switch connects to all other spine switches in a full meshD . Leaf switches connect to only one spine switchView...
When collecting information about the Power in your Data Center design you need to take into account (Select two)
When collecting information about the Power in your Data Center design you need to take into account (Select two)A . The fiber strands that are needed to support the TOR switchesB . The direction of the airflowC . The type of the voltage DC or ACD . What voltage is...