Which two backend switches support 100 GbE?
Which two backend switches support 100 GbE? A. DCS-7308 B. S5232-ON C. 29264-ON D. D4040View AnswerAnswer: BC Explanation: The two backend switches that support 100 GbE are: B. S5232-ON C. Z9264-ON Dell EMC Networking S5232-ON: Features: A 1U high-density switch with 32 ports of 100 GbE QSFP28. Supports 10/25/40/50/100 GbE...
How can they reimage a Dell PowerScale node?
A platform engineer does not have a Flash drive available. How can they reimage a Dell PowerScale node?A . Copy the OneFS install file to the node and run the isi_reimage command.B . Copy the OneFS install file onto CD and install from CD.C . Use a serial connection to...
What type of upgrade on a Dell PowerScale cluster requires the least amount of time?
What type of upgrade on a Dell PowerScale cluster requires the least amount of time?A . SimultaneousB . ParallelC . RollingD . AutomaticView AnswerAnswer: A Explanation: A simultaneous upgrade on a Dell PowerScale cluster involves upgrading all nodes at the same time. This method requires the least amount of time...
What Is the correct sequence of steps to create the cluster?
DRAG DROP A platform engineer is creating a Dell PowerScale cluster using the Configuration Wizard. They have selected the Create a new cluster option. What Is the correct sequence of steps to create the cluster? View AnswerAnswer: Explanation: The correct sequence is: Accept End User License Agreement Configure cluster name...
What does the status indicator indicate?
Exhibit. A platform engineer has connected power cables to a Dell PowerScale Gen6 node. What does the status indicator indicate?A . Not functioningB . Cold and redundantC . Mismatch of voltage or component firmwareD . On and healthyView AnswerAnswer: D Explanation: The status indicator shown in the image contains three...
How should the network cables be connected?
A platform engineer is connecting a new Dell PowerScale F600 node to the frontend switch in an existing cluster with legacy nodes. How should the network cables be connected?A . From the PCIe slot 1 to the frontend Ethernet switchB . From the PCIe slot 3 to the frontend Ethernet...
What is an important consideration when connecting Dell PowerScale Gen6 nodes to external power?
What is an important consideration when connecting Dell PowerScale Gen6 nodes to external power? A. Cable each node in a node pair to a different PDU. B. Cable all nodes to the external power feeds before connecting switch power cables. C. The total power load for all nodes in the...
What is the rack size of an F600 node?
What is the rack size of an F600 node?A . 3UB . 2UC . 1UD . 4UView AnswerAnswer: C Explanation: The Dell PowerScale F600 node occupies 1U of rack space. It is designed to provide high performance and density in a compact form factor, making it suitable for data centers...
What Is the correct sequence of steps to create the cluster?
DRAG DROP A platform engineer is creating a Dell PowerScale cluster using the Configuration Wizard. They have selected the Create a new cluster option. What Is the correct sequence of steps to create the cluster? View AnswerAnswer: Explanation: The correct sequence is: Accept End User License Agreement Configure cluster name...
What Is the correct sequence of steps to create the cluster?
DRAG DROP A platform engineer is creating a Dell PowerScale cluster using the Configuration Wizard. They have selected the Create a new cluster option. What Is the correct sequence of steps to create the cluster? View AnswerAnswer: Explanation: The correct sequence is: Accept End User License Agreement Configure cluster name...