During test process improvement it is recommended to use standards where possible. Standards originate from various sources and they cover different subjects in relation to testing Pick TWO sources of software standards, useful to software testing from the ones mentioned below. 1 credit
During test process improvement it is recommended to use standards where possible. Standards originate from various sources and they cover different subjects in relation to testing Pick TWO sources of software standards, useful to software testing from the ones mentioned below. 1 creditA . ISO 9126-1 ‘Software engineering- Product quality...
Which of the following is a valid drawback of independent testing? 1 credit
Which of the following is a valid drawback of independent testing? 1 creditA . Developer and independent testing will overlap and waste resources.B . Developers loose the sense of responsibility and independent testers may become a bottleneck.C . Independent testers need extra education and always cost more.D . Independent testers...
Which statement best explains how risk can be addressed within the testing strategy?
You have been asked to write a testing strategy for the company. Which statement best explains how risk can be addressed within the testing strategy? 1 creditA . A test strategy should address identified generic product risks and present a process for mitigating those risks in line with the testing...
Which is NOT a valid reason for using entry and exit criteria?
As part of the test strategy, entry and exit criteria will be defined for each test level. Which is NOT a valid reason for using entry and exit criteria? 1 creditA . The expectation is that development testing is not adequate.B . Exit criteria are used to decide on when...
Which TWO of the above mentioned characteristics relate to the phase test plan?
Topic 9, Scenario 9 "Test Management Documentation" A software house is concerned about the number of defects found in software released to its customers. They are starting to plan a new software product. In the past, releases have often been stopped due to poor planning and too many defects found...
Which aspect in the test estimate is the main risk in this project? 1 credit
Which aspect in the test estimate is the main risk in this project? 1 creditA . Quality of the specificationB . Availability of end-usersC . The costs of hardware and toolsD . Unknown input quality due to third party developmentView AnswerAnswer: D
The introduction of reviews and inspections has often failed as a process improvement action.
The introduction of reviews and inspections has often failed as a process improvement action. Identify the THREE most important measures that should be taken to reduce the risk that this test process improvement will fail. 2 Credits (for 2 out of 3 correct 1 credit)A . Process ownership and experienced...
To test a function, the programmer has to write a _________, which calls the function to be
To test a function, the programmer has to write a _________, which calls the function to be tested and passes it test data:A . StubB . DriverC . ProxyD . None of the aboveView AnswerAnswer: B
Which of the following, if observed in reviews and tests, would lead to problems (or conflict) within teams?
Which of the following, if observed in reviews and tests, would lead to problems (or conflict) within teams?A . Testers and reviewers are not curious enough to find defects.B . Testers and reviewers are not qualified enough to find failures and faults.C . Testers and reviewers communicate defects as criticism...
What is the main reason why reviews are especially beneficial in the above-mentioned scenario? 2 credits
What is the main reason why reviews are especially beneficial in the above-mentioned scenario? 2 creditsA . They ensure a common understanding of the product.B . They find defects early.C . They enhance project communication.D . They can be performed without exercising the code.View AnswerAnswer: D