Compared to traditional supplier relationships, a more strategic view of supplier relationships would require:

Compared to traditional supplier relationships, a more strategic view of supplier relationships would require:A . maintaining communication based on trust.B . offering the supplier more business.C . adopting electronic data interchange (EDI).D . implementing concurrent engineering.View AnswerAnswer: A Explanation: Compared to traditional supplier relationships, a more strategic view of supplier...

December 13, 2023 No Comments READ MORE +

A statistical safety stock calculation would be appropriate for:

A statistical safety stock calculation would be appropriate for:A . components used in multiple end items.B . new products at time of introduction.C . end items with stable demand.D . supply-constrained raw materials.View AnswerAnswer: C Explanation: A statistical safety stock calculation is a method to determine the optimal amount of...

December 13, 2023 No Comments READ MORE +

The benefits of standardized work include:

The benefits of standardized work include:A . consistent cycle time.B . more innovation.C . less finished goods inventory.D . shorter takt time.View AnswerAnswer: A Explanation: Standardized work is a method of organizing work processes to improve efficiency, quality, and safety1. One of the benefits of standardized work is consistent cycle...

December 13, 2023 No Comments READ MORE +

Up-to-date information about production order status is required to do which of the following tasks?

Up-to-date information about production order status is required to do which of the following tasks?A . Calculate current take time.B . Determine planned orders.C . Replenish kanban quantities.D . Calculate the cost of work in process (WIP).View AnswerAnswer: D Explanation: Up-to-date information about production order status is required to calculate...

December 13, 2023 No Comments READ MORE +

In the design and development of a manufacturing process, process engineers would most likely be responsible for decisions relating to:

In the design and development of a manufacturing process, process engineers would most likely be responsible for decisions relating to:A . lead times.B . production capacity.C . product reliability.D . routing sequences.View AnswerAnswer: D

December 13, 2023 No Comments READ MORE +

Which of the following is an example of implosion in distribution requirements planning (DRP)?

Which of the following is an example of implosion in distribution requirements planning (DRP)?A . Gathering information from several field locations and aggregating it at the manufacturing facilityB . Gathering information from the manufacturing facility and distributing it to the field locationsC . Redistributing inventory from several warehouses to one...

December 12, 2023 No Comments READ MORE +

Which of the following trade-offs should be evaluated when determining where to place inventory in a multi-echelon supply chain network?

Which of the following trade-offs should be evaluated when determining where to place inventory in a multi-echelon supply chain network?A . Production cost and lot size quantityB . Purchase cost and shrinkage ratesC . Transportation cost and delivery timeD . Customer price and order quantityView AnswerAnswer: C

December 12, 2023 No Comments READ MORE +

Work Center 1 has an available capacity of 1,200 hours per month.

Work Center 1 has an available capacity of 1,200 hours per month. Which of the following amounts represents the cumulative difference between the required capacity and the available capacity of Months 1 through 37A . 50B . 150C . 1,250D . 3,750View AnswerAnswer: B Explanation: To find the cumulative difference...

December 12, 2023 No Comments READ MORE +

Which of the following tools is used to evaluate the impact that a production plan has on capacity?

Which of the following tools is used to evaluate the impact that a production plan has on capacity?A . Demand time fence (DTF)B . Bill of resourcesC . Product routingD . Safety capacityView AnswerAnswer: B Explanation: A bill of resources is a tool that is used to evaluate the impact...

December 11, 2023 No Comments READ MORE +

An outlier has been identified in the demand data for an item. The most appropriate next step would be to:

An outlier has been identified in the demand data for an item. The most appropriate next step would be to:A . set the forecast value to the outlier limit.B . screen the outlier for manual review.C . advance the forecast model in time, without smoothing.D . increase the length of...