When does the project team determine which dependencies are discretionary?
When does the project team determine which dependencies are discretionary?A . Before the Define Activities process B. During the Define Activities process C. Before the Sequence Activities process D. During the Sequence Activities processView AnswerAnswer: D
During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?
During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?A . Monitor and Control Project Work B. Perform Quality Assurance C. Close Project or Phase D. Control ScopeView AnswerAnswer: C
Identify Risks is part of which Process Group?
Identify Risks is part of which Process Group?A . Planning B. Executing C. Closing D. InitiatingView AnswerAnswer: A
In the Plan Stakeholder Management process, expert judgment is used to:
In the Plan Stakeholder Management process, expert judgment is used to:A . Provide information needed to plan appropriate ways to engage project stakeholders. B. Ensure comprehensive identification and listing of new stakeholders. C. Analyze the information needed to develop the project scope statement. D. Decide the level of engagement of...
Which tools or techniques are used in the Plan Schedule Management process?
Which tools or techniques are used in the Plan Schedule Management process?A . Benchmarking, expert judgment, and analytical techniques B. Statistical sampling, benchmarking, and meetings C. Negotiations, pre-assignment, and multi-criteria decision analysis D. Expert judgment, analytical techniques, and meetingsView AnswerAnswer: D
Reserve analysis is a tool and technique used in which process?
Reserve analysis is a tool and technique used in which process?A . Plan Risk Management B. Plan Risk Responses C. Identify Risks D. Control RisksView AnswerAnswer: D
In which Knowledge Area is the project charter developed?
In which Knowledge Area is the project charter developed?A . Project Cost Management B. Project Scope Management C. Project Time Management D. Project Integration ManagementView AnswerAnswer: D
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:A . Project management plan. B. Project charter. C. Work breakdown structure. D. Stakeholder register.View AnswerAnswer: B
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:A . Plan Schedule Management. B. Develop Project Charter. C. Develop Schedule. D. Plan Scope Management.View AnswerAnswer: A
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:A . Cost management plan. B. Work performance information. C. Quality management plan. D. Work breakdown structure.View AnswerAnswer: A