Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.
Which time elements are relevant for lead time scheduling of a production order? Note: There are 2 correct answers to this question.A . setup timeB . Opening PeriodC . Float after ProductionD . Total replenishment lead timeView AnswerAnswer: A C Explanation: Lead time scheduling is a method of scheduling production...
What is the purpose of collective orders?
Generic Parent ยป Generic 1 pt What is the purpose of collective orders?A . To manage production orders for an entire finished product on multiple levelsB . To combine order management of co-products and by-products with the main productC . To post production costs on a cost collector instead of...
When can consumption of planned independent requirements take place for planning strategy 40 (Planning with final assembly?
When you create a sales order When can consumption of planned independent requirements take place for planning strategy 40 (Planning with final assembly?A . When MRP creates a dependent requirementB . When MRP creates a planned orderC . When you create a sales orderD . When MRP creates a planned...
Which scheduling strategy do you select?
You want to schedule an operation finitely, without removing other operations. Which scheduling strategy do you select?A . Insert operationB . Squeeze inC . Schedule in working time onlyD . Find SlotView AnswerAnswer: D Explanation: The Find Slot scheduling strategy allows you to schedule an operation finitely, without removing other...
What data can you maintain in the subitems of a bill of material (BOM)? Note: There are 2 correct answers to this question.
What data can you maintain in the subitems of a bill of material (BOM)? Note: There are 2 correct answers to this question.A . Installation pointB . Item typeC . QuantityD . Scrap percentageView AnswerAnswer: C D Explanation: The subitems of a bill of material (BOM) are the components that...
If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?
If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?A . Fill up to the maximum stock level.B . Fill up to the safety stock level.C . Fill up based on the lot size procedure.D . Fill up...
What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.
What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.A . Order typeB . Planning strategyC . Requirements profileD . Requirements typeView AnswerAnswer: B, D Explanation: The consumption of planned independent requirements by other requirements, such...
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.A . Changing the storage bin in warehouse managementB . Changing the procurement type in the product masterC . Changing the operation times in the production data structureD...
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this questionA . QueueB . Teardown timeC . Move timeD . Setup TimeView AnswerAnswer: B D Explanation: The time element of midpoint scheduled operations that can be...
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.A . To increase the number of planning levelsB . To simplify the structure of bills of materialC . To reduce the number of material mastersD . To make the assignment of components easierE . To...