To which objects can a personnel number be directly assigned? Note: There are 2 correct answers to this question?
To which objects can a personnel number be directly assigned? Note: There are 2 correct answers to this question?A . Planner groupB . Maintenance planC . Work centerD . Business partnerView AnswerAnswer: C D Explanation: A personnel number is a unique identifier for an employee in the SAP system. A...
Which options do you have in SAP S/4HANA Asset Management, Public Cloud Edition? Note: There are 2 correct answers to this question
Which options do you have in SAP S/4HANA Asset Management, Public Cloud Edition? Note: There are 2 correct answers to this questionA . You can configure SAP S/4HANA Cloud via the self-service configuration UI.B . You have access to the SAP S/4HANA back-end systemC . You can configure SAP S/4HANA...
Which steps are available for the maintenance technician when using the Report Malfunction bile? Note: There are 3 correct answers to this question.
Which steps are available for the maintenance technician when using the Report Malfunction bile? Note: There are 3 correct answers to this question.A . Select and print the maintenance order shop papersB . Display the current location of the technical objectC . Add a URL to provide further informationD ....
The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100% which date is relevant for the calculation of future planned dates if the maintenance work is delayed?
The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100% which date is relevant for the calculation of future planned dates if the maintenance work is delayed?A . Planned date of the next call, independent of maintenance order datesB . Actual...
Which settings must be customized to set up Inspection Checklist processing? Note: There are 2 correct answers to this question
Which settings must be customized to set up Inspection Checklist processing? Note: There are 2 correct answers to this questionA . Maintain settings at plant level for usage decisions.B . Create a control key which expects inspection characteristic assignmentsC . Assign an Inspection Type to a Maintenance Order Type and...
Which scheduling parameters are used in a multiple-counter plan? Note: There are 2 correct answers
Which scheduling parameters are used in a multiple-counter plan? Note: There are 2 correct answers to this question.A . Scheduling periodB . Start dateC . Scheduling indicatorD . Factory calendarView AnswerAnswer: A C Explanation: A multiple-counter plan is a maintenance plan that contains multiple maintenance cycles based on different counters....
Which functions characterize a Strategic analysis as opposed to embedded analysis within the SAP S/4HANA core system? Note: There are 2 correct answers to this question
Which functions characterize a Strategic analysis as opposed to embedded analysis within the SAP S/4HANA core system? Note: There are 2 correct answers to this question A. Preconfigured Core Data Service (CDS) containing SQL views B. A collection of tools that are not included with core SAP S/4HANA C. SAP...
Which of the following are components of cloud-based SAP Intelligent Asset Management? Note: There are 2 correct answers to this question
Which of the following are components of cloud-based SAP Intelligent Asset Management? Note: There are 2 correct answers to this questionA . Worker Safety applicationsB . SAP Asset Performance ManagementC . SAP Work ManagerD . SAP Service and Asset Manager (formerly SAP Asset Manager)View AnswerAnswer: B D Explanation: SAP Intelligent...
Which of the following is a prerequisite for external refurbishment?
Which of the following is a prerequisite for external refurbishment?A . Define the order type for external refurbishment.B . Select the material group for externally refurbished materials.C . Assign an external work center to a maintenance order operationD . Activate the subcontracting indicator in an external activity.View AnswerAnswer: D Explanation:...
Which objects have been enhanced with linear data in maintenance processes? Note: There are 3 correct answers to this question
Which objects have been enhanced with linear data in maintenance processes? Note: There are 3 correct answers to this questionA . Maintenance plan headerB . Work order confirmationC . Maintenance plan itemD . Equipment task listE . Notification itemView AnswerAnswer: B C E Explanation: Linear data is used to describe...