Which of the following defines the term 'issue'?

Which of the following defines the term 'issue'?A . A problem which is now or is about to breach delegated tolerances for work on a project or programme.B . A problem which occurs on a day-to-day basis which could have an immediate impact on a project.C . A problem which...

August 22, 2024 No Comments READ MORE +

Which of these statements is FALSE?

Which of these statements is FALSE?A . Stakeholders may be for the change or againstB . Stakeholders may have little influence or lotsC . Stakeholders may be internal or external to your organisationD . Stakeholders with high influence always have high interest in the projectView AnswerAnswer: D

August 22, 2024 No Comments READ MORE +

The purpose of a risk register is to provide a:

The purpose of a risk register is to provide a:A . structured process for risk identification.B . record of the ownership of risk and issue management actions.C . means of assessing the likelihood and impact of all of the risks.D . record of risks, their impact and the actions taken...

August 22, 2024 No Comments READ MORE +

Which of the following can be adjusted during a time box? 1) Scope 2) Resource 3) Time 4) Quality

Which of the following can be adjusted during a time box? 1) Scope 2) Resource 3) Time 4) QualityA . 1 and 2 onlyB . 1 and 4 onlyC . 3 and 4 onlyD . 2 and 4 onlyView AnswerAnswer: B

August 22, 2024 No Comments READ MORE +

One advantage of virtual communications is:

One advantage of virtual communications is:A . that nonverbal signals can have an impact on discussions.B . it's easy to detect signs of conflict within the project team.C . access to a wider resource pool for the project.D . that the project team will always be co-located.View AnswerAnswer: C

August 21, 2024 No Comments READ MORE +

Which of the following is not an output of a critical path analysis?

Which of the following is not an output of a critical path analysis?A . Total and free float.B . Earliest start time and latest finish time of activities.C . Project completion time.D . Cost-benefit analysis.View AnswerAnswer: D

August 21, 2024 No Comments READ MORE +

Which one of the following is not considered in resource management?

Which one of the following is not considered in resource management?A . Identifying resources.B . Influencing resources.C . Assigning resources to activities.D . Matching resources to the schedule.View AnswerAnswer: B

August 21, 2024 No Comments READ MORE +

The purpose of project progress reporting is to:

The purpose of project progress reporting is to:A . ensure a simpler critical path.B . enable the tracking of project deliverables.C . ensure stakeholder acceptance of project deliverables.D . provide an increased total float.View AnswerAnswer: B

August 21, 2024 No Comments READ MORE +

Which one of the following statements BEST defines procurement?

Which one of the following statements BEST defines procurement?A . A technique to establish the best approach for obtaining the resources for the projectB . A group of interrelated resources and activities that transform inputs into outputsC . The description of the purpose, form and components to support delivery of...

August 21, 2024 No Comments READ MORE +

Which of the following is an activity in a typical configuration management process?

Which of the following is an activity in a typical configuration management process?A . Evaluation.B . Identification.C . Registration.D . Justification.View AnswerAnswer: B

August 20, 2024 No Comments READ MORE +