How should DSDM team measure progress?
How should DSDM team measure progress?A . Through a project dashboard B. Based on what has been delivered at the end of a Timebox. C. Based on the completion of activities rather than the delivery of products D. Through an analysis of the Instrumental Success Factors.View AnswerAnswer: B
Which of the following is NOT an interest into which each DSDM role is grouped?
Which of the following is NOT an interest into which each DSDM role is grouped?A . Business B. Solution/Technical C. Management D. MaintenanceView AnswerAnswer: C
Which of the following is a DSMD principle?
Which of the following is a DSMD principle?A . Build incrementally from firm foundations B. Build incrementally from Feasibility onwards C. Build incrementally in Timeboxes D. Build incrementallyView AnswerAnswer: A
When initially creating MoSCoW priorities, what is the primary focus?
When initially creating MoSCoW priorities, what is the primary focus?A . Project priorities B. Project increment priorities C. Timebox priorities D. Iterative Development prioritiesView AnswerAnswer: A
According to the DSDM principle ‘Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?
According to the DSDM principle ‘Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?A . During evolutionary development B. At the start of the project C. When the Business Advisor is available D. Whenever the level of solution quality is known.View...
When should the quality of the evolving solution first be tesed?
When should the quality of the evolving solution first be tesed?A . At the end of a Timebox B. At the end of a project. C. At the end of each increment D. As part of the iterative Development processView AnswerAnswer: D
How does DSDM differ from most other Agile approaches?
How does DSDM differ from most other Agile approaches?A . It focuses on the entire project lifecycle B. It focuses on the development of products C. It focuses on the delivery of products D. It focuses on the collaborative working of teamsView AnswerAnswer: A
What DSDM Principles requires the transparency of all work being performed by the team?
What DSDM Principles requires the transparency of all work being performed by the team?A . Principle 1- Focus on the Business Need B. Principle 1 C Build incrementally from Firm Foundations C. Principle 66-Develop iteratively D. Principle 8-Demonstrate ControlView AnswerAnswer: D
When is a Timebox Plan updated?
When is a Timebox Plan updated?A . At the Daily Start-ups B. At Timebox Kick-ups C. As needed by the Project Manager D. Each time a Timebox is completedView AnswerAnswer: D
Which statement applies to the DSDM process?
Which statement applies to the DSDM process?A . Can be configured and calibrated to cater for light or strong governance B. DSDM projects can deliver the phases in the DSDM process in any order C. Does not require the elaboration of supporting products for complex projects D. Provides an approach...