Suppliers are stakeholders of a project management plan because they:
Suppliers are stakeholders of a project management plan because they:
A . contribute to the project’s procurement strategy.
B . help satisfy the project’s resource requirements.
C . provide acceptance certificates based on quality of resources supplied.
D . determine the quality requirements of goods supplied.
Answer: B