Shift factors are set to 100% which date is relevant for the calculation of future planned dates if the maintenance work is delayed?
The maintenance engineer creates a strategy plan with the call object maintenance order.
Shift factors are set to 100% which date is relevant for the calculation of future planned dates if the maintenance work is delayed?
A . Planned date of the next call, independent of maintenance order dates
B . Actual finish date of the maintenance order
C . The date of the final confirmation
D . Technical completion date of the maintenance order
Answer: D