When setting-up a program, planned ROI% is calculated based on: (Choose two.)
When setting-up a program, planned ROI% is calculated based on: (Choose two.)A . Values in the NPV field.B . Values in the Planned cost field.C . Values in the Planned return field.D . Values in the Budgeted cost field.View AnswerAnswer: BC
Plugins may be added to the base platform in one of the following ways: (Choose three.)
Plugins may be added to the base platform in one of the following ways: (Choose three.)A . Activated by an admin (not by default).B . Activated by an it_portfolio_manager.C . Requested from ServiceNow.D . Activated by default in the base ServiceNow system.E . Activated by an it_pps_admin.View AnswerAnswer: ACD
What does the project status report allow project managers to do? (Choose two.)
What does the project status report allow project managers to do? (Choose two.)A . View the project Gantt chartB . View the WBSC . Show historical trend of project KPI’sD . Print as a PDF attachmentView AnswerAnswer: CD
Where do you define ‘Roles’ requested via resource plans?
Where do you define ‘Roles’ requested via resource plans?A . Resource roles under resource management.B . No need to define it differently, they are same are system rolesC . Under skill management modulesD . Roles under system securityView AnswerAnswer: A
The PPM Standard plugin enables an it_project_manager to perform the following activities: (Choose three.)
The PPM Standard plugin enables an it_project_manager to perform the following activities: (Choose three.)A . Determine overall project cost requirementsB . Configure cost type definitionC . Define target for the portfolioD . Establish resource requirements and track costs.E . Track actual amount spent compared to an approved budget.View AnswerAnswer: ADE
How does a project manager request a change to a resource plan in the requested state?
How does a project manager request a change to a resource plan in the requested state?A . Use notes on resource plan.B . Email resource user.C . Request change on resource planD . Email resource managerView AnswerAnswer: C
If Scenario Planning for PPM is installed, a portfolio manager can access the Portfolio Planning Workbench by navigating to which of the following? (Choose two.)
If Scenario Planning for PPM is installed, a portfolio manager can access the Portfolio Planning Workbench by navigating to which of the following? (Choose two.)A . Project moduleB . Program WorkbenchC . Portfolio Planning related linkD . Portfolio Planning Workbench moduleView AnswerAnswer: CD
The Project Portfolio Management application supports domain separation at this level:
The Project Portfolio Management application supports domain separation at this level:A . Level 3 C Tenant self-managed configurationB . Level 1 C Tenant data managementC . Level 2 C Tenant process managementD . Data onlyView AnswerAnswer: D
To use the Time Sheet dashboard, what plugin must be installed?
To use the Time Sheet dashboard, what plugin must be installed?A . Common ITSM Service Portal Application Components (com.snc.app_common.service_portal)B . Employee Service Center (com.sn_hr_service_portal)C . Knowledge Management C Service Portal (com.snc.knowledge_serviceportal)D . Performance Analytics C Content Pack C PPM Standard plugin (com.snc.pa.pmo_dashboards)View AnswerAnswer: D