When should centralized decision-making be used?
When should centralized decision-making be used?A . When there are significant economies of scale B. When making frequent decisions C. When decisions need specific local context D. When decisions are short-term in durationView AnswerAnswer: A Explanation: It makes little economic sense to have duplication of effort, misalignment, or inequity. One...
What are two Release Train Engineer responsibilities? (Choose two.)
What are two Release Train Engineer responsibilities? (Choose two.)A . Build an effective Product Owner/Product Management team B. Understand Customer needs; validate Solutions C. Manage and prioritize the flow of work to the ART D. Facilitate Pl Planning readiness and the event itself E. Drive relentless improvement through Inspect and...
Why are big Stories considered an anti-pattern?
Why are big Stories considered an anti-pattern?A . They make it difficult to apply iterative development B. They make it difficult to estimate testing efforts C. They make it difficult to estimate compliance efforts D. They do not support Pair WorkView AnswerAnswer: A Explanation: Bug Stories are difficult to complete...
What is a Product Owner (PO) anti-pattern in Iteration planning?
What is a Product Owner (PO) anti-pattern in Iteration planning?A . The PO changes priorities of the already refined intent B. The PO brings in changes to the planned Features based on stakeholder feedback from the System Demo C. The PO introduces the business intent to the team for the...
What is the primary measurement during Inspect and Adapt?
What is the primary measurement during Inspect and Adapt?A . Number of automated tests B. Number of Features delivered C. Team NPS score D. Program predictability measureView AnswerAnswer: D Explanation: One primary metric is the program predictability measure. Each team's planned vs. actual business value is rolled up to create...
What are three opportunities for creating collaboration on a team? (Choose three.)
What are three opportunities for creating collaboration on a team? (Choose three.)A . Backlog refinement B. iteration planning C. Pair work D. Hackathons E. Communities of Practice F. Inspect and AdaptView AnswerAnswer: A,B,C Explanation: Three opportunities are Backlog refinment, Iteration planning, Pair work.
What is the purpose of the Large Solution Level in SAFe?
What is the purpose of the Large Solution Level in SAFe?A . To effectively operate in a highly regulated environment B. To coordinate the work of multiple Agile Teams C. To identify and eliminate waste in the process D. To coordinate multiple Agile Release Trains that develop the same SolutionView...
What are two actions the Scrum Master should take?
During Iteration Review, the team decides to carry forward three Stories to the next lteration. This is the second time during this Pl that some of the team’s Stories are carried over. What are two actions the Scrum Master should take? (Choose two.)A . Discuss the issue at the lteration...
What should the Scrum Master consider doing?
One state on the team Kanban board has people waiting while the previous stage is overloaded. What should the Scrum Master consider doing?A . Call for a Team and Technical Agility self-assessment so that the team agrees on improvement actions B. Ask the team to redesign the board C. Encourage...
Which action is part of the initial capacity planning process?
An organization is conducting their first Program Increment Planning session, and the new teams are asked to provide their capacity. Which action is part of the initial capacity planning process?A . Compare final team capacity across all teams and make individual team adjustments B. Subtract one point for every team...