How far into the future does a Solution Roadmap forecast?
How far into the future does a Solution Roadmap forecast?A . The upcoming PIB . Multiple yearsC . The next 2-3 PI'sD . One yearView AnswerAnswer: B Explanation: Multiple years
How can the Architect help resolve the situation?
An ART is defining a new Architectural Runway for a future PI. A senior developer approaches the System Architect with concerns that the developers do not have the knowledge to implement the Enablers. How can the Architect help resolve the situation?A . Hire contractors to implement the EnablersB . Involve...
What must System Architect avoid when balancing intentional architecture and emergent design for the upcoming PI?
What must System Architect avoid when balancing intentional architecture and emergent design for the upcoming PI?A . Explaining the architectural Vision to Agile TeamsB . Providing guidance to align the team's localized design decisionsC . Un-validated architectural decisionsD . Reuse of common componentsView AnswerAnswer: C Explanation: Un-validated architectural decisions
What is one piece of work a System Architect demos during Iteration Review?
What is one piece of work a System Architect demos during Iteration Review?A . Intentional architectureB . Coding standardsC . Architectural documentationD . New system functionalityView AnswerAnswer: A Explanation: Intentional architecture
What is one benefit of capacity allocation?
What is one benefit of capacity allocation?A . It balances effort between business Feature and Enabler developmentB . It ensures that Architects are working form a prioritized backlogC . It guarantees that there are enough people on the ART to deliver everythingD . It prioritizes technical debt reduction over business...
Which is one of the activities of Pre-Plan?
Which is one of the activities of Pre-Plan?A . ART-level risks are ROAM'ed by the Solution TrainB . ART predictability measures are created by Solution ManagementC . ART leaders determine how they will address upcoming capabilities in their PI planning eventsD . Agile Teams participate in a confidence voteView AnswerAnswer:...
During which activity do Architects provide teams feedback on the actual value delivered from architecture work?
During which activity do Architects provide teams feedback on the actual value delivered from architecture work?A . Throughout PI PlanningB . During Value Stream MappingC . Prior to or part of the I&A System DemoD . During the Coach Sync meetingView AnswerAnswer: C Explanation: Prior to or part of the...
How could the System Architect could respond as a lean-Agile leader?
A senior developer on a new ART approaches a System Architect with concerns that Agile processes will not work in organization. How could the System Architect could respond as a lean-Agile leader?A . Refer the developer to an Agile coachB . Highlight the personal and organization benefits of an Agile...
What has the most influence on the portfolio canvas and Vision?
What has the most influence on the portfolio canvas and Vision?A . Portfolio budgetsB . Enterprise architectureC . The operational Value StreamD . Strategic ThemesView AnswerAnswer: D Explanation: Strategic Themes
What is one attribute of Agile architecture?
What is one attribute of Agile architecture?A . It is a phase gated approachB . It supports a continuous flowC . It decouples deployment from releaseD . It is shared the responsibility between System Architects and Agile TeamsView AnswerAnswer: C Explanation: It decouples deployment from release